Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam

Western I ndonesia National Roads I mprovement Project 36 b Appraisal procurement is under process.

14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang

Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai IIP2JN on January 2014. • After CTC s review of the documents, comments were transmitted in the form of a MEMO DINAS to Balai II thru the Directorate of Implementation in Region I. • Revised LARAP documents from P2JN Consultant resubmitted in June 2014. • LARAP documents submitted to World Bank on November 2014. B. Pending Issues, Concern and Actions a LARAP documents still to be issued by World Bank for NOL. C. Update during this reporting month of December 2014 a World Bank issued on December 2014 the No Objection Letter to the LARAP documents. b Documents still to be approved by World Bank.

15. Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel

Province : Sumatera Utara A. Previous Status : • CTC received the Draft Final LARAP documents on September 30,2013 from Balai. • PMU submitted the documents to World Bank on October 28, 2013 requesting further review and acceptance. • On October 28, 2013, World Bank returned to PMU the documents with comments to be considered in finalizing the documents for resubmission. • On October 31, 2013, PMU requested the Director of Implementation Affairs thru SatkerPPK to address the World Bank comments • Revised LARAP documents was resubmitted to World Bank on January 30, 2014 • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • PPKSatker and the Local Government started the preparation stage of land acquisition B. Pending Issues, Concern and Actions a LARAP implementation under preparation stage by SATKERPPK. b Appraisal result still to be finalized prior to negotiation with the land owners and subsequent payments of the PAP. C. Update during this reporting month of December 2014 a Appraisal result for two 2 out of the six 6 sub-districts affected by the road improvement are ready for negotiation b Compensation payment documentations are under process.