Monitoring Report of the LARAP Package No. 3

Western I ndonesia National Roads I mprovement Project 32 • On November 18, 2013 the Director of Planning issued a letter to the Director of Implementation Affairs Region 1, that the LARAP documents can now be implemented in the acquisition of Right of Ways and removal of construction obstructions. B. Pending Issues, Concern and Actions a PMUCTC is awaiting the LARAP implementation Report from SATKER b Relocation of 1 kiosk still to done. C. Update during this reporting month of December 2014 a No update this month.

6. Monitoring Report of the LARAP Package No. 6

: Pasar Pedati - Kerkap Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. B. Pending Issues, Concern and Actions a LARAP s implementation still to be implemented by SATKER. C. Update during this reporting month of December 2014 a Compensation payments under process and Monitoring Report to be submitted to World Bank by January 2015.

7. Monitoring Report of the LARAP Package No. 7

: Indrapura - Tapan Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai IIP2JN on January 2014 • After CTC s review of the documents, comments were transmitted in the form of a MEMO DINAS to Balai II thru the Directorate of Implementation in Region I. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. • LARAP documents approved by World Bank on October 14, 2014. B. Pending Issues, Concern and Actions a LARAP Implementation Report to be prepared and submitted to PMUCTC for Western I ndonesia National Roads I mprovement Project 33 review. b No allocated budget in 2014 for payment of land acquisition. c Implementation cost of LARAP will be included by Local Government in the 2015 budget. C. Update during this reporting month of December 2014 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

8. Monitoring Report of the LARAP Package No. 8

: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC s comments requesting the documents for revision in line with CTC s comments. • Revised LARAP documents from P2JN Consultant resubmitted in June 2014. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of December 2014 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang Kota Agung Province : Lampung A. Previous Status : • LARAP documents are still to be prepared. B. Pending Issues, Concern and Actions a Still no issues and concerns. C. Update during this reporting month of December 2014 a Nothing to report this period. b Proposed to be replaced.