Monitoring Report of the LARAP Package No. 6

Western I ndonesia National Roads I mprovement Project 34

10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam

Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC s comments requesting the documents for revision in line with CTC s comments • Revised LARAP documents from P2JN Consultant resubmitted in June 2014. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of December 2014 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko

Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Monitoring Report for compensation payments of 81 out of 183 PAP have been submitted to World Bank. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. b Compensation payments for the remaining 102 PAP is in process . C. Update during this reporting month of December 2014