Monitoring of Environmental Aspects During Construction

Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 20

4.6.2.2 Social Issues 1.

Monitoring Report of the Larap for Krui - Biha Larap report of the package for Krui Biha in Lampung Province already approved the World Bank dated 4 January 2013, and approval the monitoring report dated 18 April 2013. The pending issue is a partially affected mosque redevelopment. Local Governmentproject will rebuild an affected mosque in parallel with construction work. Contract signing for the package of Krui – Biha dated 25 Nov 2013.

2. Monitoring Report of the Larap for Padang Sawah – Sp. Empat

Larap report of the package for Padang Sawah – Sp. Empat in West Sumatera Province already approved the World Bank dated 13 January 2013, and approval the monitoring report dated 19 July 2013. The pending issue is the remaining of 21 affected people not yet received compensation from Local Government. Now the compensation payment for 21 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready. Contract signing for the package of Padang Sawah – Sp. Empat dated 6 Dec 2013.

3. Monitoring Report of the LARAP for Manggopoh – Padang Sawah

Larap report of the package for Manggopoh – Padang Sawah in West Sumatera Province already appoved the World Bank dated 4 January 2013, and approval the monitoring reports dated 18 April 2013. The pending issue is the remaining of 10 affected people not yet received compensation from Local Government. CTC had been received proof of compensation payment for 5 from the remaining of 15 affected people during January 2014. Now the compensation payment for 10 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready. Contract signing for the package of Manggopoh – Padang Sawah dated 6 Dec 2013.

4. Monitoring Report of the LARAP for Ipuh – Bantal

Larap report of the package for Ipuh – Bantal in Bengkulu Province was approved the World Bank dated 10 December 2012. Up to the end of December 2013 CTC already receive a proof of compensation payment for 157 of the total 217 affected peoples. A monitoring report submitted to the World Bank from PMU dated 24 December 2013, and received some comment to the report from the World Bank dated 6 January 2014. Compensation payment for the remaining of 60 PAP being resolved by Local Government and will be submitted to the World Bank at the end of February 2014. Contract signing for the package of Ipuh – Bantal dated 14 Nov 2013.

5. Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung Tampak

Larap report of the package for Sp. Gunung Kemala – Pugung Tampak in Lampung