Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung Tampak

Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 21 Province has reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 and need revision as follows: a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the Sp Gunung Kemala – Pugung Tampak links. Likewise the established price standard for the building compensation should refer to the current data updated data. b. Action plan table should include a formation of the land apprasing team, b moving 83 units of electricity utilities. c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanantion some data with no name in the nominative list. e. Action plan signewd by the relevan local government as a commitment that the local government will provide proper budget for the action plan f. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. Gunung Kemala – Pugung Tampak. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC waiting a report of Larap implementation from Satker in Lampung Province.

6. Report of LARAP for Sp. Rampa - Poriaha

Larap report for Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 and need revision as follows: a. Moving and providing compensation for one person kiosk owner affected must including to the action plan. b. Action plan signed by the relevan local government as a commitment that the local government will provide proper budget for the action plan c. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the world bank review and PMU letter, CTC revised the Larap report for Sp. Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 22 Rampa – Poriaha. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the world bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC waiting a report of Larap implementation from Satker in Lampung Province.

7. Report of Five Larap in Bengkulu

CTC recieved Larap Reports for five 5 packages in Bengkulu Province from the BBPJN III Palembang dated 30 September 2013. The five of Larap reports consists Larap for Package No. 13: Sp. Rukis – Tanjung Kemuning, Larap for Package No. 6: Psr Pedati – Kerkap, Larap for Package No. 11: Muko-muko – Bantal, Larap for Package No. 16: Seblat – Ipuh, Larap for Package No. 16: Bintunan – Lais. CTC reviewed the five 5 Larap Reports, and already submitted to the world bank from PMU dated 13 November 2013. All of the five Larap reports in Bengkulu Province has reviewed by the World Bank Ref.WINRIP144 dated 20 November 2013 and need revision as follows: a. All five Larap reports that that there are some assets land and building that will be affected entirely. Following the LARPF WINRIP should be covered on land acquisition and resettlement and need to budgeted. b. On the Larap report for package for Ipuh – Seblat there are 126 land plots belong to governmentpublic that are affected. However the social economic survey and the inventory table do not show the situasion. According to world bank letter, PMU via Ref. 1476Bp.11MD2013 dated 27 November 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addresed above. A revision for five Larap reports had been submitted to the World Bank on 9 January 2014, and PMU had been received some comments from WB 16 January 2014. All of the Bank’s request will be provided by PMU on the Larap monitoring report.

8. Report of LARAP for Sibolga – Bts Tapsel

CTC received Draft Final Larap report for Sibolga – Bts Tapsel from Balai dated 30 September 2013. The Larap report already submitted to the world Bank from PMU dated 22 October 2013, and approval the world bank dated 28 October 2013. Larap report for Sibolga – Bts Tapsel in North Sumatera Province has reviewed by the World Bank Ref.WINRIP140 dated 28 October 2013 and need revision as follows: a. There are some renters will be affected by the project which is also categoized as project affected people so must be recorded in the affected people list.