Civil Works Implementation WINRIP DOC MPR CTC MPR No.13 2014 01 2014 01 09 00225.

Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 17 documentation and reporting based on the Quality Assurance Plan QAP. They will prepare a Quality Assurance system covering all aspects of quality in all subprojects, and continuously monitor the effectiveness of their supervision procedures. Quality Assurance Engineer of the CTC has been mobilized on July 01, 2013. On 11 December 2013, an interaction meeting with the DSC CO-Team Leader and Project Officer of PMU to discuss Quality Assurance Plan QAPQuality Assurance System. DSC shall develop Quality Assurance Plan Quality Assurance System and subsequently report to the Balai for approval. Quality Assurance Engineer had also scheduled to visit site which could not take place.

4.6 Environmental and Social Considerations

4.6.1 Current Overall Situation

A project category is assigned to each package as either Category A, B or C depending on the likely degree of influence on environmental issues with a brief explanation as follows Appendix D. Category A project is one which will have a significant negative impact on the environment and may have an influence on areas outside the actual project area. A project classified as such requires an AMDAL ANDAL, RKLRPL study. Category B project is one which affects the people or the environment to some extent but with a smaller impact than a Category A. The required environmental analysis is a UKLUPL study only. Category C project has minimal effect on the people or environment and an environmental analysis is not required. Standard operational procedures SOP or SKPPL are used to handle any minor problem which may arise. Details of packages that require environmental and social safeguard are given in Appendix No. 8 and the following table provides a summary of the work involved in the 21 WINRIP packages. Works Program No of Packages No of Investigations Approval by Remarks BLH World Bank AWP-1 4 8 SPPL x 4 Full LARAP x 4 4 SPPL 4 Full LARAP Approved – NOL issued by WB, except for SPPL AWP-2 8 17 Simple LARAP x 1 Full LARAP x 8 AMDAL Study x 4 UKLUPL x 4 4 UKLUPL 3 AMDAL 1 SLARAP 1 one Study AMDAL for threes packages, are Packages No.7, 12 and 14 packages on AWP2 AWP3. 1 one Study AMDAL for two packages, are Packages No.11 16. packages on AWP2