Package No. 08: Bts Kota Pariaman – Manggopoh Social Issues:

Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 53

6.6.10. Package No. 10: Sp. Empat – Air Balam Social Issues:

CTC received the LARAP report from Balai II PadangPMU on 01 August 2013. Review and comment from CTC was sent to PMU on 9 September 2013, and PMU forward to P2JNLocal Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues: Official Letter from Director of Implementation Affairs Rgion I to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding request submitted the AMDAL. Then on 27 December 2013 AMDAL document already sent to Director of Implementation Affairs Rgion I with Official Letter from Kepala Balai Besar Pelaksanaan Jalan Nasional II. The AMDAL document was submit to the World on 20 January 2014.\ Official Letter from Director of Implementation Affairs Rgion I to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding request submitted the AMDAL. Then on 27 December 2013 AMDAL document already sent to Director of Implementation Affairs Rgion I with Official Letter from Kepala Balai Besar Pelaksanaan Jalan Nasional II. The AMDAL document is still process submitted to the World Bank.

6.6.11. Package No. 11: Bantal - Mukomuko Social Issues:

CTC received a Larap report of package for Pasr. Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalization the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report had been submitted to the World Bank dated 9 January 2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report, and 3 land appraisal value used as reference for conducting negotiation. Now, the WB request is under preparation by Satker I Bengkulu. Environmental Issues: AMDAL document not yet complete, and CTC waiting for the report from P2JN Bengkulu