Monthly Progress Report January 2014
Western I ndonesia National Roads I mprovement Project 49
6.6 Environmental and Social Impact Issues
6.6.1 Package No. 01: Krui – Biha
Social Issues:
The Larap report of package for Krui – Biha in Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report has been submitted to the
World Bank from PMU dated 10 April 2013. The World Bank has reviewed the report dated 18 April 2013 require revision to be provided by DGH.
According to the World Bank request, CTC revised a monitoring report, and submit to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank from PMU
dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Contract signing for the package of Krui – Biha dated 25 Nov 2013.
Environmental Issues:
A SPPL already sent to Bank from PMU dated 30 September 2013.
6.6.2. Package No. 02: Padang Sawah – Simpang Empat. Social Issues:
The Larap report of package for Padang Sawah – Simpang Empat West Sumatera Province has already approved by the World Bank dated 13 January 2013, and the monitoring report
has been submitted to the World Bank from PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 require revision to be provided by DGH.
According to the World Bank request, CTC revise a monitoring report, and submit to PMU dated 5 July 2013. A monitoring report has been submitted to the World Bank from PMU
dated 15 July 2103, and approval from the World Bank dated 19 July 2013. The project has the remaining of 21 affected people not yet received compensation from Local Government.
Now CTC waiting a proof of the compensation payment for 21 affected people from local government. Contract signing for the package of Padang Sawah – Sp. Empat dated 6 Dec
2013.
Environmental Issues:
Official Letter from Director of Implementation Affairs Region I to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding request submitted the
SPPL. Then on 27 December 2013 SPPL document already sent to Director of Implementation Affairs Rgion I with Official Letter from Kepala Balai Besar Pelaksanaan
Jalan Nasional II. The SPPL document was submit to the World Bank on 20 January 2014.
Monthly Progress Report January 2014
Western I ndonesia National Roads I mprovement Project 50
6.6.3. Package No. 03: Manggopoh – Padang Sawah Social Issues:
The Larap report of package for Manggopoh - Padang Sawah West Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report has
been submitted to the World Bank from PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 require revision to be provided by DGH.
According to the World Bank request, CTC revise a monitoring report, and submit to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank from PMU
dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people not yet received compensation from Local
Government. Now CTC waiting a proof of the compensation payment for 15 affected people from local government. Contract signing for the package of Manggopoh – Padang Sawah
dated 6 Dec 2013.
Environmental Issues:
Official Letter from Director of Implementation Affairs Rgion I to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding request submitted the
SPPL. Then on 27 December 2013 SPPL document already sent to Director of Implementation Affairs Rgion I with Official Letter from Kepala Balai Besar Pelaksanaan
Jalan Nasional II. The SPPL document was submit to the World Bank on 20 January 2014.
6.6.4. Package No. 04: Ipuh – Bantal Social Issues:
The Larap report of package for Ipuh – Bantal was approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of 217
PAPs from Head of Satker PJN II Bengkulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank
dated 24 December 2013, and now waiting a comment from the World Bank.Contract signing for the package of Ipuh – Bantal dated 14 Nov 2013.
Environmental Issues:
CTC has received copy document a SPPL report as the environmental safeguards of the package for Ipuh – Bantal from Environmental Agency BLHD and P2JN Bengkulu.
Regarding to the implementation of the Review Mission on December 9 to 11 December 2013 in Provinces of Bengkulu and comments from the World Bank Environmental Expert
related to the safeguards environmental documents for package No 4: Ipuh Bantal, then based on observations in field and the regulations required environmental safeguards
more then SPPL.