Design Integration, Road Safety aspects and Monitoring of Environmental Studies

Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 20

4.6.2.2 Social Issues 1.

Monitoring Report of the Larap for Krui - Biha Larap report of the package for Krui Biha in Lampung Province already approved the World Bank dated 4 January 2013, and approval the monitoring report dated 18 April 2013. The pending issue is a partially affected mosque redevelopment. Local Governmentproject will rebuild an affected mosque in parallel with construction work. Contract signing for the package of Krui – Biha dated 25 Nov 2013.

2. Monitoring Report of the Larap for Padang Sawah – Sp. Empat

Larap report of the package for Padang Sawah – Sp. Empat in West Sumatera Province already approved the World Bank dated 13 January 2013, and approval the monitoring report dated 19 July 2013. The pending issue is the remaining of 21 affected people not yet received compensation from Local Government. Now the compensation payment for 21 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready. Contract signing for the package of Padang Sawah – Sp. Empat dated 6 Dec 2013.

3. Monitoring Report of the LARAP for Manggopoh – Padang Sawah

Larap report of the package for Manggopoh – Padang Sawah in West Sumatera Province already appoved the World Bank dated 4 January 2013, and approval the monitoring reports dated 18 April 2013. The pending issue is the remaining of 10 affected people not yet received compensation from Local Government. CTC had been received proof of compensation payment for 5 from the remaining of 15 affected people during January 2014. Now the compensation payment for 10 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready. Contract signing for the package of Manggopoh – Padang Sawah dated 6 Dec 2013.

4. Monitoring Report of the LARAP for Ipuh – Bantal

Larap report of the package for Ipuh – Bantal in Bengkulu Province was approved the World Bank dated 10 December 2012. Up to the end of December 2013 CTC already receive a proof of compensation payment for 157 of the total 217 affected peoples. A monitoring report submitted to the World Bank from PMU dated 24 December 2013, and received some comment to the report from the World Bank dated 6 January 2014. Compensation payment for the remaining of 60 PAP being resolved by Local Government and will be submitted to the World Bank at the end of February 2014. Contract signing for the package of Ipuh – Bantal dated 14 Nov 2013.

5. Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung Tampak

Larap report of the package for Sp. Gunung Kemala – Pugung Tampak in Lampung Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 21 Province has reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 and need revision as follows: a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the Sp Gunung Kemala – Pugung Tampak links. Likewise the established price standard for the building compensation should refer to the current data updated data. b. Action plan table should include a formation of the land apprasing team, b moving 83 units of electricity utilities. c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanantion some data with no name in the nominative list. e. Action plan signewd by the relevan local government as a commitment that the local government will provide proper budget for the action plan f. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. Gunung Kemala – Pugung Tampak. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC waiting a report of Larap implementation from Satker in Lampung Province.

6. Report of LARAP for Sp. Rampa - Poriaha

Larap report for Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 and need revision as follows: a. Moving and providing compensation for one person kiosk owner affected must including to the action plan. b. Action plan signed by the relevan local government as a commitment that the local government will provide proper budget for the action plan c. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the world bank review and PMU letter, CTC revised the Larap report for Sp.