Package No. 04: Ipuh – Bantal Social Issues:

Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 51 Therefor the PMU has requested considerations technical from to Head of Subdirectorate of Environmental and Road Safety by the formal letter dated 16 Desember 2013 and the Subdit Environmental Affairs and Road Safety letter on 30 January 2014 was recommended that package No. 4 Ipuh-Bantal should apply UKLUPL.

6.6.5. Package No. 05: Sp. Rampa – Poriaha Social Issues:

The Larap report of package for Sp. Rampa – Poriaha North Sumatera Province has already submitted to the World Bank from PMU dated 30 August 2013. The World Bank has reviewed the report dated 16 September 2013 require revision to be provided by DGH. According to the World Bank request, CTC revise a Larap report, and submit to PMU dated 29 October 2013. Larap report has been submitted to the World Bank from PMU dated 6 November 2103, and approval from the World Bank dated 12 November 2013 that the documents disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC is waiting report of implementation of the Larap from Head of Satker II Lampung Province. Environmental Issues: The UKLUPL already sent to the World Bank from PMU dated 30 September 2013.

6.6.6. Package No. 06: Psr. Pedati – Kerkap Social Issues:

CTC received a Larap report of package for Pasr. Pedati – Kerkap from Balai IIIPalembangPMU dated 7 October 2013. CTC has reviewed to finalization the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2013 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report had been submitted to the World Bank dated 9 January 2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report, and 3 land appraisal value used as reference for conducting negotiation.Now, the WB request is under preparation by Satker I Bengkulu. Monthly Progress Report January 2014 Western I ndonesia National Roads I mprovement Project 52 Environmental Issues: The UKLUPL was sent to Bank on 30 September 2013

6.6.7. Package No. 07: Indrapura – Tapan Social Issues:

CTC received from Balai IIP2JN Padang Larap report of package for Indrapura – Tapan during January 2014. Now, the report is being reviewed by CTC. Environmental Issues: Now CTC waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.8. Package No. 08: Bts Kota Pariaman – Manggopoh Social Issues:

CTC received the LARAP report from Balai II PadangPMU dated 01 August 2013. Review and comment from CTC was sent to PMU dated 9 September 2013, and PMU forward to P2JNLocal Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues: Official Letter from Director of Implementation Affairs Rgion I to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding request submitted the AMDAL. Then on 27 December 2013 AMDAL document already sent to Director of Implementation Affairs Rgion I with Official Letter from Kepala Balai Besar Pelaksanaan Jalan Nasional II. The AMDAL document was submit to the World on 20 January 2014.

6.6.9. Package No. 09: Rantau Tijang – Kota Agung Social Issues:

This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear. Environmental Issues: This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear.