Monitoring Report of the Larap for Padang Sawah – Sp. Empat
Monthly Progress Report January 2014
Western I ndonesia National Roads I mprovement Project 21
Province has reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 and need revision as follows:
a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the Sp
Gunung Kemala – Pugung Tampak links. Likewise the established price standard for the building compensation should refer to the current data updated data.
b. Action plan table should include a formation of the land apprasing team, b moving 83 units of electricity utilities.
c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanantion some data with no name in the nominative list.
e. Action plan signewd by the relevan local government as a commitment that the local
government will provide proper budget for the action plan f.
Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September
2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above.
Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. Gunung Kemala – Pugung Tampak. A revision of the Larap report already submitted to the
WB from PMU dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.
Referring to letter from the World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of
the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC waiting a report of Larap implementation from Satker in Lampung
Province.