Monthly Progress Report January 2015
Western Indonesia National Roads Improvement Project 61
6.6.10 Package No.10: Sp. Empat
– Air Balam Social Issues:
Implementation cost of LARAP to be included by Local Government in 2015 budget. Affected assets inventory and measurement is by Land Acquisition Committee from Local
Government.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design. Visit to site is scheduled on February 2015.
6.6.11 Package No.11: Bantal - Mukomuko
Social Issues:
Mo itori g ‘eports of the LA‘AP’s i ple e tatio for compensation payment of 58 PAP from
190 PAP already submitted for to World Bank. Environmental Issues:
CTC submitted to PMU the draft report for the integration of AMDAL recommendation into the design.
6.6.12 Package No12: Kambang
– Indrapura Social Issues:
Implementation cost of LARAP to be included by Local Government in 2015 budget. Affected assets inventory and measurement is by Land Acquisition Committee from Local
Government.
Environmental Issues:
CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental issues which integrated in to the design. Visit to site is scheduled on February 2015.
6.6.13 Package No.13: Sp. Rukis
– Tj. Kemuning Social Issues:
Mo itori g ‘eports of the LA‘AP’s i ple e tatio ha e to e prepared a d su
itted for review and for submission to World Bank.
Affected assets inventory and measurement is by Land Acquisition Committee from Local Government.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design. Visit to site is scheduled on February 2015.
Monthly Progress Report January 2015
Western Indonesia National Roads Improvement Project 62
6.6.14 Package No.14: Painan
– Kambang Social Issues:
Implementation cost of LARAP to be included by Local Government in 2015 budget. Monitoring Report of LARAP implementation have to be prepared and submitted for review and
for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design. Visit to site is scheduled on February 2015.
6.6.15 Package No.15: Sibolga
– Bts. Tapsel Social Issues:
LARAP implementation Monitoring Report from SatkerPPK still to be submitted to PMUCTC for review and for submission to World Bank. The recommendation not yet considered in the design.
Environmental Issues:
Draft Integration of UKLUPL recommendation into the design has been submitted to PMU. The recommendations are not yet considered in the design.
6.6.16 Package No.16: Sebelat
– Ipuh Social Issues:
Mo itori g ‘eports of the LA‘AP’s i ple e tatio for compensation of payments for the 139
PAP have to be prepared and submitted for review and for submission to World Bank. LARAP documents covers only the road link. If there are land acquisition for the bridge site,
separate LARAP documents need to be prepared
Environmental Issues:
CTC submitted to PMU the draft report for the integration of AMDAL recommendations into the design.
6.6.17 Package No.17: SP. Gunung Kemala
– Pg. Tampak Social Issues:
LARAP implementation report is not yet submitted by Satker 1 Lampung to PMUCTC. Procurement of appraiser is on-going. Compensation payment target in March to June 2015.
Environmental Issues:
CTC submitted to PMU the draft report for the integration of AMDAL recommendations into the design.
6.6.18 Package No.18: Mukomuko
– Bts. Sumbar Social Issues:
Monthly Progress Report January 2015
Western Indonesia National Roads Improvement Project 63
Still no issues and concerns
Environmental Issues:
The contract package is proposed to be replaced.
6.6.19 Package No.19: Lais - Bintunan
Social Issues:
Mo itori g ‘eports of the LA‘AP’s i ple e tatio ha e to e prepared a d su
itted for review and for submission to World Bank.
Compensation payment is under process and monitoring report to be submitted to World Bank on February 2015.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design. Site Visit scheduled on February 2015.
6.6.20 Package No.20: Lubuk Alung
– Sicincin Social Issues:
Implementation cost of LARAP to be included by Local Government in 2015 budget.
Environmental Issues: Draft Report on recommendation for the integration of UKLUPL in the design has been
submitted to PMU.
6.6.21 Package No.21: Lubuk Alung
– Kuraitaji Social Issues:
Implementation cost of LARAP to be included by Local Government in 2015 budget.
Environmental Issues: Draft Report on recommendation for the integration of UKLUPL in the design has been
submitted to PMU.
Monthly Progress Report January 2015
Western Indonesia National Roads Improvement Project 64
6.7 Management Information System
The hosting company of winrip-ibrd.com server has done migration of server from VPS-XEN to VPS-KVM. The hosting server storing almost all applications and websites of WINRIP. So
the migration process is very important for the sustainability of applications and websites of WINRIP.
There are a few things done in the server migration process, namely: • Cha ges i the co trol pa el.
• Upgrade of the e ser er a d data ase ser er. • I creasi g the capacity a d ‘AM of the ser er.
• Cha ge the IP address of the ser er.
In the user side, the migration process is not affected at all. Because the applications and websites of WINRIP looks normal as usual. However, in the administrator side, the migration
process is very beneficial. Among them is the increase in capacity of server from 25 GB to 50 GB.
This capacity increase has been changing our paradigm. Originally we had planned to use NAS server for storage of WINRIP files. Because of the greater capacity of server hosting,
then we put the database and documents on the server hosting with subdomain address http:dms.winrip-ibrd.com.
And in February we will be doing testing of DMS and storage application on the server hosting. This testing process will involve the supporting staff. Those who will manage and
update the content of the DMS applications.
6.7.1 Server Hosting Migration
1 Preparation
Before starting the migration of server hosting, we have to backup all of data. Which is backed up of databases and script files of all applications and websites.
The backup process handy in case when the server migration process failed. So that we can still do the recovery. And all applications and websites stay safe and run normally.
Here is a list of database and files backups that we have done.
NO. APPLICATIONS
DATABASE FILES
1 CHS
22.5 KB 8.02 MB
2 FMIS
55.7 KB 40.9 MB
3 Storage
--- 2.88 GB
4 Website
2.57 MB 32.5 MB
Monthly Progress Report January 2015
Western Indonesia National Roads Improvement Project 65
This proved useful, because after the server migration process then the FMIS and website was an error. So we do a recovery database of FMIS and website. After that the FMIS and
WINRIP website back to normal.
2 Migration Process
The migration process is change the system and capacity of the VPS services, from VPS-XEN to VPS-KVM. The hosting company also increasing the capacity and larger of RAM with same
rental price. Because in 2015, they are no longer using the VPS-XEN server. Time limit of server migration is until the end of January 2015. And for the life time of the
VPS-XEN server is at the end of February 2015. After the limit the VPS-XEN servers will be shut down.
All the migration process is done by the hosting company. They help for control panel installation, upgrade web server and database server. While we do a backup of the database
and files.
NO. MIGRATION
1 Installation of control panel
2 Upgrade and setting up of web server
3 Upgrade and setting up of database server
4 Increase of capacity and RAM
5 New IP address http:103.229.72.181
The impact of this migration process is changing the IP address of server from http:49.50.8.125 to http:103.229.72.181. So we have to do re-pointing DNS of winrip-
ibrd.com domain to the new IP address. Pointing process of IP address has using the control panel that provided by the hosting company.
3 Migration Results
The migration process of server gives us some advantages. The biggest advantage is the addition of server capacity up to 50 GB and RAM up to 16 GB.
The bigger capacity has been changing our paradigm. Originally we had planned to use NAS server for storage of WINRIP files. Because of the greater capacity of server hosting, then we
put the database and documents on the server hosting with subdomain address http:dms.winrip-ibrd.com.
Meanwhile the addition of 16 GB of RAM make increasing server performance. Then the server work becomes faster and stable.
Monthly Progress Report January 2015
Western Indonesia National Roads Improvement Project 66
Here is the results of the migration process of server.
NO. MIGRATION
RESULTS
1 Control panel
Has been upgraded 2
Web server Has been upgraded
3 Database server
Has been upgraded 4
Capacity Increased to 50 GB
5 RAM
Increased to 16 GB 6
IP address Changed to http:103.229.72.181
6.8 Quality Assurance
In January no site visit journey undertaken by Quality Assurance Engineer, problems that occur in the field are reported based on reports received from SEfield team which
are to be solved as soon as possible.
Package No. 1 : Biha – Krui
Cash flour of contractor is inadequate Contract of still have no permit to setup the base camp and missing license from quarry still
not issued yet by the local government. Package No. 2 : Padang Sawah
– Simpang Empat Production or delivery of RCPs and construction of reinforced concrete U – ditches are too
late. Production of aggregates for road widening and granular pavement has been stopped due to
uarry’s UKLUPL is ot yet appro ed. Asphalt mixing plant often out of order.
Constructions of Air Gadang Bridge have not yet started. Package No. 3 : Manggopoh
– Padang Sawah Asphalt mixing plant often out of order.
Inadequate number of unit of dump truck Package No. 4 : Ipuh
– Bantal Huge negative slippage
Mismanagement between lead contractor and the joint operation partner.
Activities of the Quality Assurance Engineer are shown in Appendix D.
6.9 Project Risks and Mitigation Measures
6.9.1 Risks Related to Delays
Since the detailed engineering design DED is under responsibility of the Design and Supervision Consultant DSC, delay on DSC establishment affected to the procurement of
AWP-2 and AWP-3 sub-projects. As discussed previously above, the DED of several subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. The CTC