Monitoring of Environmental Aspects During Construction

Western Indonesia National Roads Improvement Project 30 B. Pending Issues, Concern and Actions a Existing mosque is partially traversed due widening of the existing travelled way. b Due to resistance to partially demolished and rebuild the mosque, a new action plan is proposed, where the road alignment centerline will be shifted to the other side. c Land acquisition is required on the other side of the road centerline alignment if the new action plan push through. C. Update during this reporting month of January 2015 a On-going construction b No Update this period

2. Monitoring Report of the LARAP Package No. 2 : Padang Sawah

– Sp. Empat Province : Sumatera Barat A. Previous Status :  LARAP documents approved by World Bank on January 13, 2013  Monitoring Report approved by World Bank on July 19, 2013  Additional LARAP documents approved by World Bank on July 21, 2014 B. Pending Issues, Concern and Actions a Compensation for 24 PAP along the road link is in appraisal stage proceedings by Independent Appraisal. b Price negotiation between the Land Acquisition Committee and 3 of 5 remaining PAP along Air Gadang Bridge site is on-going. c Monitoring Report concerning the payments to the remaining affected persons still to be prepared for submission to World Bank. C. Update during this reporting month of January 2015 a On-going construction b Compensation payments for 27 from the remaining fourty five 45 PAP are resolved by the local government.

3. Monitoring Report of the LARAP Package No. 3

: Manggopoh – Padang Sawah Province : Sumatera Barat A. Previous Status :  LARAP documents approved by World Bank on January 4, 2013  Monitoring Report approved by World Bank on April 18, 2013  Monitoring Report for compensation payments for five 5 of the affected persons out of the remaining fifteen 15 persons was submitted to World Bank on February 28, 2014.  Monitoring Report for compensation payment for 8 of the affected persons out of the 10 remaining persons and 67 from 68 new PAP was submitted to World Bank on June 19, 2014. Western Indonesia National Roads Improvement Project 31 B. Pending Issues, Concerns and Actions a Documents for compensation payments for two 2 remaining identified PAP was witheld by the Local Government. b Monitoring Report concerning compensation payments to the one 1 identified PAP still to be prepared for submission to World Bank. C. Update during this reporting month of January 2015 a Compensation payments for 2 of the remaining 3 PAP were resolved by the Local Government. b No update this month.

4. Monitoring Report of the LARAP Package No. 4 : Ipuh

– Bantal Province : Bengkulu A. Previous Status :  LARAP documents approved by World Bank on December 10, 2012  Monitoring Report for payments for 157 affected persons out of the 227 Project Affected Persons was submitted by PMU to World Bank on December 24, 2013  Monitoring Report for the compensation of the remaining 70 affected persons was submitted by PMU to the World Bank on February 28, 2014.  World Bank sent letter to PMU on March 5, 2014 informing that the Bank have no further comment on the Monitoring Report. B. Pending Issues, Concern and Actions a Monitoring Report for the compensation payments of additional 30 PAP still to be submitted to World Bank. C. Update during this reporting month of January 2015 a On-going construction. b Monitoring Report for the compensation payments of additional 30 PAP is under review and finalization by CTC.

5. Monitoring Report of the LARAP Package No. 5

: Sp. Rampa – Poriaha Province : Sumatera Utara A. Previous Status :  World Bank accepted the revised LARAP documents and issued No Objection Letter on November 12, 2013.  On November 18, 2013 the Director of Planning issued a letter to the Director of Implementation Affairs Region 1, that the LARAP documents can now be implemented in the acquisition of Right of Ways and removal of construction obstructions. B. Pending Issues, Concern and Actions a PMUCTC is awaiting the LARAP implementation Report from SATKER concerning the completed relocation of the kiosk. C. Update during this reporting month of January 2015 a Kiosk has already been removed and relocated.