Document Library System, used to record all information of document and
Western Indonesia National Roads Improvement Project 46
No. Action
By Whom Status and Target Dates
services 15.
Send the Expression for Manifestation of Interest for the Capacity Enhancement on Disaster Risk Mitigation to the Bank
Send the draft Request for Proposals PMU and CTC
End of January February 16, 2015
16. Send a revised version of the procurement plan
February 2, 2015 17.
Finalize the bid evaluation reports for packages 6 and 19 NCB full e-procurement
PMU January 30, 2015
18. Send the bid evaluation report for package 15 to the Bank
PMU March 16, 2015
19. Send the evaluation report for package 5 to the Bank
PMU January 21, 2015
20. Send the engineering designs for packages 7, 8, 10 and 12 to the
Bank PMU
January 26, 2015 21.
Send the engineering designs for packages 14, 16, 20 and 21 to the Bank
PMU February 2, 2015.
22. Send the bidding documents for packages 8, 10 and 12 to the Bank
March 2, 2015 23.
Publish the bidding document for package 7 NCB March 2, 2015
24. Formalize the agreement on the design review for pack. 1
If the quarry permit is not issued by end of January, take action to facilitate the permit or oblige the contractor to find another
quarry PMUContractor
DGH management
End of January 2015 By mid-February if the
quarry permit is not issued
25. Reach an agreement on the field engineering including the bridge
design for package 2 PMUContractor
February 16, 2015 26.
Reach an agreement on the field engineering for package 3 Carry out a show case meeting for package 3
February16, 2015 February 27, 2015
27. Carry out the 2nd show case meeting for package 4
February 16, 2015 28.
Report back to the Bank on how DGH has implemented the recommendations of the auditors in the auditing report of the 2012
and 2013 financial statements End of January 2015
29. Revised disbursement plan for 2015
February 16, 2015 30.
Meet with the Inspectorate General of Ministry of Public Works for inclusion of all project packages financed into their work program
Bank February 16, 2015
31. Provide comments on the revised PMM, including the web
application Bank
January 30, 2015 32.
Comply with Anticorruption Action Plan agreements in annex 9 PMUCTC
As per deadline in annex 9
33. Put MTR report on WINRIP website
PMUCTC January 30, 2015
34. Provide comments to the draft terms of reference for the Technical
Audits PMU
End of January 2015 35.
Send to the Bank a request for modification of the contract with CTC
PMU January 30, 2015
36. Carry out some random checks
to erify if DGH’s AADT data is correct and use a simple regression analysis to compare it with the
data from the mobile survey CTC
February April 15, 2015
37. Regularly submit the quarterly progress reports to the Bank
PMU Each calendar quarter
38. Send a draft of the restructuring request to the Bank
PMU End of February 2015
Western Indonesia National Roads Improvement Project 47