Monitoring Report of the LARAP Package No. 4 : Ipuh Monitoring Report of the LARAP Package No. 5

Western Indonesia National Roads Improvement Project 33

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang – Kota Agung Province : Lampung A. Previous Status :  Proposed to be replaced. B. Pending Issues, Concern and Actions a Proposed to be replaced. C. Update during this reporting month of January 2015 a Nothing to report this period. b Proposed to be replaced.

10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat

– Sp. Air Balam Province : Sumatera Barat A. Previous Status :  LARAP documents submitted to World Bank on August 7, 2014.  LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of January 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

11. Monitoring Report of the LARAP Package No. 11

: Bantal - Mukomuko Province : Bengkulu A. Previous Status :  PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.  World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.  Monitoring Report for compensation payments of 81 out of 183 PAP have been submitted to World Bank. B. Pending Issues, Concern and Actions a Mo itori g ‘eports of the LA‘AP’s i ple e tatio ha e to e prepared a d submitted for review and for submission to World Bank. b Compensation payments for the remaining 51 PAP is in process and to be paid from 2015 National Budget. C. Update during this reporting month of January 2015 a The remaining 58 PAP’s Mo itori g ‘eport for co pe satio still to be prepared and submitted to World Bank by January 2014. Western Indonesia National Roads Improvement Project 34

12. Monitoring Report of the LARAP Package No. 12

: Kambang - Indrapura Province : Sumatera Barat A. Previous Status :  LARAP documents approved by World Bank on October 14, 2014. B. Pending Issues, Concern and Actions a No allocated budget to pay land acquisition in the 2014 budget of the Local Government. Compensation payments to be allocated from the 2015 budget. C. Update during this reporting month of January 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

13. Monitoring Report of the LARAP Package No. 13

: Sp. Rukis – Tj. Kemuning Province : Bengkulu A. Previous Status :  PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.  World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Mo itori g ‘eports of the LA‘AP’s i ple e tatio ha e to e prepared a d submitted for review and for submission to World Bank. C. Update during this reporting month of January 2015 a Affected assets inventory and measurements is under process by BPNLand Acquisition Committee. b Appraisal procurement is under process.

14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang

Province : Sumatera Barat A. Previous Status :  LARAP documents submitted to World Bank on November 2014.  World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. B. Pending Issues, Concern and Actions a LARAP implementation is scheduled on March 2015. C. Update during this reporting month of January 2015 a No update this period.

15. Monitoring Report of the LARAP Package No. 15 : Sibolga

– Bts. Tapsel Province : Sumatera Utara A. Previous Status :