Technical Assistance for Capacity Building for Disaster Risks Reduction
4.2 Procurements
Procure e t shall e co ducted u der the Ba k’s Procure e t Procedures as e tio ed i the Loa Agreement. The International Competitive Bidding ICB based on the Bank letter Ref. WINRIP136 will apply to the packages with the construction estimated cost more than US 25 Million to comply with the e Ba k’s threshold for ICB. Accordi g to the GOI regulatio , a pre ualificatio shall e applied for the packages with the construction estimated cost more than IDR 10 Billion. Review from previous procurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojects qualification still used Pre-Qualification and for remaining sub-project must be process with Post Qualification. As well as for all NCB the World Bank also requested to follow Post Qualification in procurement process. All subprojects for WP-1 have been started with prequalification since 30 December 2011 for ICB multiple contract. This was an advanced procurement action agreed by both DGH and the World Bank prior to the CTC establishment. All AWP-1 sub-projects had signed the contract. The last 2 sub-projects, Package 02: Pd. Sawah – Simpang Empat and Package 03: Manggopoh – Padang Sawah, signed the contract on December 6, 2013 and NOL for disbursement for all 4 packages had been issued by the World Bank on December 10, 2013. As of the reporting month January 2014, a more detailed current updates are fully indicated in Sub-Chapter 1.4 Procurement on Page 3 of this Report and consolidated project status in a tabulated format shown in Table 1.1 on page 8 of this Report. Under Category 3 of Loan Agreement there are three 3 consultancy packages namely ; 1. Capacity Building For Disaster Risks Reduction 2. Capacity Building For Environmental Management 3. Capacity Building For Road Safety Co sulta t for Capacity Buildi g For Disaster ‘isks ‘eductio is still to e procured, hile the other t o 2 consultancy packages are proposed to be deleted.. A more detailed updates can be found in Sub-Chapter 1.5 Procurement on Page 7 of this Report.
Draft of Request For Expression of Interest is being finalized by TLKJ, while Terms of Reference has been finalized awaiting issuance of No Objection Letter NOL from World Bank.. The WINRIP updated Procurement Plan is attached as Appendix F.4.3 Civil Works Implementation
All 4 contract packages under AWP-1 are currently under construction by different contractors. Commencement of works for all the 4 packages commenced on the 2 nd week of January 2014. As of to date, there are three 3 new sub-projects that were awarded to the winning bidders with the signing of Contract Agreements between the Government of Indonesia and the winning Contractors. Two 2 of the contract packages are under implementation schedule AWP-2 and the other contract package is under AWP-3.Parts
» WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» World Bank Implementation Review Mission and Site Visit
» Package 17 Sp. Gunung Kemala – Pugung Tampak AWP-3.
» Package 11 Bantal – Mukomuko AWP-2
» Package 13 Sp. Rukis – Tj. Kemuning AWP-2
» Packages 5 Simpang Rampa – Poriaha AWP-2
» Package No. 6 Pasar Pedati – Kerkap AWP-2 Package No.19 Lais – Bintunan AWP-3
» Package No.15 Sibolga – Batas Tapsel AWP-3
» Technical Assistance for Capacity Building for Disaster Risk Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Consolidated Update of the Progress of the Project
» Background WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Project Development WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Project Objective CTC Consultants
» DSC Consultants WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Procurements WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Civil Works Progress WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 18.71 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 40.41 29.11 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» - 33.14 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Quality Assurance WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Monitoring of Environmental Aspects During Construction
» Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» Monitoring Report of the LARAP Package No. 4 : Ipuh Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10 : Sp. Empat
» Monitoring Report of the LARAP Package No. 11
» Monitoring Report of the LARAP Package No.16 : Seblat - Ipuh
» Monitoring Report of the LARAP Package No.17 : Sp. Gunung Kemala
» Monitoring Report of the LARAP Package No.18 : Mukomuko
» Monitoring Report of the LARAP Package No.19 : Lais - Bintunan
» Monitoring Report of the LARAP Package No. 20 : Lubuk Alung - Sicincin
» Monitoring Report of the LARAP Package No. 21 : Lubuk Alung - Kurataji
» Anti Corruption Issues WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Road Safety Audit WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Letter Database System, used to record all information of incoming and
» Document Library System, used to record all information of document and
» World Bank and GOI Compliance
» Implementation Support Components WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Environmental and Social Impact Issues
» Management Information System WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» Project Risks and Mitigation Measures
» Current Situation Actions Required
» 2.38 II WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 1.20 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 28.83 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 2.97 IV WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 2.15 VI WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 1.28 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 21.90 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 2.09 VIII WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 2.64 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 67.46 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 5.62 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 18.06 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 31.58 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 46.36 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 60.68 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 74.81 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 83.98 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 91.27 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 96.16 100.00 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 3.71 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 5.98 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 11.28 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 16.08 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» -0.12 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» EXECUTI VE SUMMARY 5. WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 16.08 P WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 29.11 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» 15.814 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» -48.74 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
» -10.11 WINRIP DOC MPR CTC MPR No.25 2015 01 2015 01 12 00224.
Show more