Monitoring Report of the LARAP Package No. 2 : Padang Sawah Monitoring Report of the LARAP Package No. 3

Western Indonesia National Roads Improvement Project 32

6. Monitoring Report of the LARAP Package No. 6

: Pasar Pedati - Kerkap Province : Bengkulu A. Previous Status :  PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.  World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a SATKER still to submit to PMU the LARAP Monitoring Report for the compensation payment for 546 out of 602 PAP. b Remaining 56 from the 602 PAP to be paid from 2015 National Budget. C. Update during this reporting month of January 2015 a Compensation payments for 546 out of the 602 PAP were already paid.

7. Monitoring Report of the LARAP Package No. 7 : Indrapura - Tapan

Province : Sumatera Barat A. Previous Status :  LARAP documents approved by World Bank on October 14, 2014. B. Pending Issues, Concern and Actions a LARAP Implementation Report to be prepared and submitted to PMUCTC for review. b No allocated budget in 2014 for payment of land acquisition. c Implementation cost of LARAP will be included by Local Government in the 2015 budget. C. Update during this reporting month of January 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

8. Monitoring Report of the LARAP Package No. 8

: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status :  LARAP documents submitted to World Bank on August 7, 2014.  LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of January 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going. Western Indonesia National Roads Improvement Project 33

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang – Kota Agung Province : Lampung A. Previous Status :  Proposed to be replaced. B. Pending Issues, Concern and Actions a Proposed to be replaced. C. Update during this reporting month of January 2015 a Nothing to report this period. b Proposed to be replaced.

10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat

– Sp. Air Balam Province : Sumatera Barat A. Previous Status :  LARAP documents submitted to World Bank on August 7, 2014.  LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of January 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

11. Monitoring Report of the LARAP Package No. 11

: Bantal - Mukomuko Province : Bengkulu A. Previous Status :  PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.  World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.  Monitoring Report for compensation payments of 81 out of 183 PAP have been submitted to World Bank. B. Pending Issues, Concern and Actions a Mo itori g ‘eports of the LA‘AP’s i ple e tatio ha e to e prepared a d submitted for review and for submission to World Bank. b Compensation payments for the remaining 51 PAP is in process and to be paid from 2015 National Budget. C. Update during this reporting month of January 2015 a The remaining 58 PAP’s Mo itori g ‘eport for co pe satio still to be prepared and submitted to World Bank by January 2014.