Package 13 Sp. Rukis Tj. Kemuning AWP-2
6. Package No.19 Lais Bintunan AWP-3
This sub-project is under implementation schedule AWP-3. The project roadline is located in the Province of Bengkulu having an approximate length of 10.80 kilometers. The Contract Package is procured thru the National Competitive Bidding NCB using the method of e-procurement system of procuring the works. As mentioned in previous monthly progress report, there were three 3 applicant contractors who submitted their bids on December 29, 2014 and bids were opened on the same day. All the three 3 bidders are sole entity Contractors. The applicant bidders who submitted their bids are as follows : • PT. Maras Bangun Persada : Rp. 32,929,110,000 • PT. Rodatekindo Purajaya : Rp. 33,689,459,000 • PT. Sumber Tratindo Utama : Rp. 31,758,052,000 The lowest canvassed bid is submitted by PT. Sumber Tratindo Utama with an amount of Rp. 31,758,052,000 which is 11.18 below the approved Owner s Estimate of Rp. 35,756,587,000, while the 2 nd lowest bid is submitted by PT. Maras Bangun Persada in the amount of Rp. 32,929,110,000 or 7.91 lower than the Owners s Estimate. Bid Evaluation Report has been finalized and announcement of winner by POKJA was made on February 13, 2015. Based on the Bid Evaluation Report BER and post-review of the qualification of the 1 st and 2 nd lowest bidders, both failed to quality due to lack of related work experience and failed to met the minimum required financial resources. As no complain from the two 2 disqualified bidders was received during the complain period, PPK issued letter of acceptance on February 23, 2015 to POKJA s recommendation to award the contract to the 3 rd lowest responsive bidder, PT. Rodatekindo Purajaya. It is expected that contract signing will be executed during the 1 st week of March 2015.7. Package No.15 Sibolga Batas Tapsel AWP-3
This sub-project is included in the implementation schedule AWP-3. The Project road is 36 kilometers long and located in the Province of Sumatera Utara. The Contract Package is procured thru post qualification criteria and International Competitive Bidding ICB method using the Full e-Procurement System. As originally scheduled, bids were submitted on February 23, 2015 and bids were opened at 10:15 a.m, on the same day at BALAI I Office in Medan.Parts
» WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» World Bank Implementation Review Mission and Site Visit
» Package 17 Sp. Gunung Kemala Pugung Tampak AWP-3.
» Package 11 Bantal Mukomuko AWP-2
» Package 13 Sp. Rukis Tj. Kemuning AWP-2
» Packages 5 Simpang Rampa Poriaha AWP-2
» Package No. 6 Pasar Pedati Kerkap AWP-2
» Package No.19 Lais Bintunan AWP-3 Package No.15 Sibolga Batas Tapsel AWP-3
» Technical Assistance for Capacity Building for Disaster Risk Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Consolidated Update of the Progress of the Project
» Background WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Project Development WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Project Objective WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» CTC Consultants WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» DSC Consultants WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Procurements WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Civil Works Progress WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 21.04 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 44.25 30.11 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» - 33.85 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Quality Assurance WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Monitoring of Environmental Aspects During Construction
» Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» External Monitoring Report SatkerPPK to BLH for Implementation of
» Monitoring Report of the LARAP Package No. 2 Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7 Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam
» Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
» Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
» Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20 : Lubuk Alung - Sicincin
» Monitoring Report of the LARAP Package No. 21 : Lubuk Alung - Kurataji
» Anti Corruption Issues WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Road Safety Audit WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Letter Database System, used to record all information of incoming and
» Document Library System, used to record all information of document and
» World Bank and GOI Compliance
» Implementation Support Components WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Environmental and Social Impact Issues
» System Design Management Information System
» Project Risks and Mitigation Measures
» 0.29 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.82 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 2.88 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.65 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 3.00 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.94 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 2.20 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 4.86 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 2.16 1.91 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 35.31 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 47.72 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 65.59 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 84.21 100.00 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 4.69 2.95 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 3.530 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 3.95 - WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.06 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 7.877 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.77 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 20.359 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.96 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 44.25 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.61 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.03 - WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 8.04 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 5.95 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 24.30 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.12 21.76 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» -14.27 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» -11.88 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
Show more