Western I ndonesia National Roads I mprovement Project 4-11
• World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP
documents for implementation. B. Pending Issues, Concern and Actions
a Remaining 56 from the 602 PAP to be paid from 2015 National Budget. C. Update during this reporting month of February 2015
a Monitoring Report concerning the compensation payment for 546 out of 602 PAP still to be prepared for submission to World Bank.
7. Monitoring Report of the LARAP Package No. 7
: Indrapura - Tapan Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. B. Pending Issues, Concern and Actions
a LARAP Implementation Report to be prepared and submitted to PMUCTC for review.
b No allocated budget in 2014 for payment of land acquisition. c Implementation cost of LARAP will be included by Local Government in the 2015
budget. C. Update during this reporting month of February 2015
a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.
8. Monitoring Report of the LARAP Package No. 8
: Bts. Pariaman - Manggopoh Province
: Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions
a Implementation cost of LARAP will be included by the Local Government in the 2015 budget.
C. Update during this reporting month of February 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of
Local Government are on-going.
9. Monitoring Report of the LARAP Package No. 9
: Rantau Tijang Kota Agung Province
: Lampung
A. Previous Status : •
Proposed to be replaced. B. Pending Issues, Concern and Actions
Western I ndonesia National Roads I mprovement Project 4-12
a Proposed to be replaced. C. Update during this reporting month of January 2015
a Nothing to report this period. b Proposed to be replaced.
10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam
Province : Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions
a Implementation cost of LARAP will be included by the Local Government in the 2015 budget.
C. Update during this reporting month of February 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of
Local Government are on-going.
11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
Province : Bengkulu
A. Previous Status : •
PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections.
• World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP
documents for implementation. •
Monitoring Report for compensation payments of 81 out of 183 PAP have been submitted to World Bank.
B. Pending Issues, Concern and Actions a Compensation payments for the remaining 51 PAP is in process and to be paid
from 2015 National Budget. C. Update during this reporting month of February 2015
a The remaining 58 PAP s Monitoring Report for compensation already submitted to World Bank dated February 6, 2015.
12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
Province : Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. B. Pending Issues, Concern and Actions
a No allocated budget to pay land acquisition in the 2014 budget of the Local Government. Compensation payments to be allocated from the 2015 budget.