Procurements WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
Western I ndonesia National Roads I mprovement Project 4-4
At the end of this reporting month of February 2015, all the four 4 contract packages were still
lagging farther behind schedule. The situation remains the same as in previous month as four 4 of the contract packages continue to follow a downward trend of delayed schedules. Sub-project
progress schedule of Krui Biha Package 1 has been revised regarding to additional cost of various order.
With the remaining time left of less than 50
of the contract time for all of the four 4 contract packages, the Contractors will have hard time to deliver the Works on the target dates of
completion, unless a workable and realistic action plans or Catch-up Schedules will be enforced by the Contractors.
Package No. 1 : Biha Krui Inspite of the high level meeting between the DGH and Contractors that was held in December
2014 in Padang wherein the main agenda were to resolved all issues and major problems that hampered the progress of the works, the expectation from the Contractor to deliver positive
outcome never happened. It is evident that the Contractor never attempted to put the works toward attaining good progress as only 2.32 of the works was accomplished during the whole
month of February 2015. The problem of slow and delayed progress have been going-on ever since the work commenced
some fourteen 14 months ago. With only 35 or 227 calendar days of the contract time are left for the remaining 79 of the works to be done, the target date of completion in mid October 2015
may never be realized unless the Contractor will work double time and additional equipmentworking group on a realistic workable action plan in the coming months ahead.
As the period ended, the overall actual physical work progress is only 21.04 of the scheduled progress of 35.31 toward the end of the month. In other words, there was a huge deficit of
delayed works or an slippage of -14.27 behind schedule. To be timelized this Project on time, the Contractor showed reach the progress 10 per month.
Some of the major problems that should be given more attention to resolve by the Contractor are inadequate cash flow, shortage of labor for drainage works and insufficient supply of aggregates for
base and asphalt mix.
A more detailed status of this Package is presented in ANNEX P-I Executive Summary Report. Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge
As of end this month the total overall work progress is 44.25
against scheduled progress of 56.13
which is still behind schedule by -11.88
. In this reporting month February 2015, the progress showed signs of slight down trend again.
Major problems that are still unresolved are the carryover problems from previous months such as the frequent breakdown of the Asphalt Mixing Plant where the bulk of the progress depends on
and the redesign of the sub-structure of Air Gadang Bridge which is still under discussion to get approval of foundation design.
To date, the delayed work is still on a manageable level, but it is still a bit of concern that unless the current problems are addressed immediately, the delayed works will further fall behind in the
coming months. ANNEX P-2 Executive Summary Report present a more detailed status of the Contract Package.