21.04 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.

Western I ndonesia National Roads I mprovement Project 4-5 Package No. 3 : Manggopoh Padang Sawah The current overall work progress of only 30.11 against scheduled progress of 58.67 since the works commenced 14 month ago is of much concern due to the very limited remaining contract time left. As of end of this month, the remaining contract time is only 43 or 315 calendar days with still 70 of the works to be completed. At the end of this reporting month February 2015 the slippage went farther down to -28.56 from previous month s slippage of -22.57 in December 2014. If the average accomplishment of close to only 5 per month progress attained for the past four 4 months will not improve to at least twice the previous monthly work output in coming months, the Project will never be completed on the target date of completion on the early part of January 2016 unless the Contractor will work double time to implement a realistic and workable action plan. The problem of slow and delayed work progress have be going-on for the past seven 7 months. Problem which the Contractor have to prioritize and give more attention to resolve are the frequent out of order of the Asphalt Mixing Plant, inadequate number of units of dump truck, shortage of labor for drainage works and low output of the crusher plant to produce quantity of aggregate requirements. Due to urgency to maximize the output of paving works to attain a good monthly progress, the Contractor shall maintain the AMP regularly and address and resolve all issues that are presently hampering the progress of the works. The main problem in February the Local Government closed the Contractor basecamp with in 10 days due to MIS under preparation the new regulation of basecamp and Quarry Exploitation Permit. A more detailed status of the project progress are shown in ANNEX P-3 Executive Summary Report . Package No. 4 : Ipuh Bantal As of end this month the total overall work progress is 21.76 against scheduled progress of 55.61 which is stice behind schedule by 33.85. In this Reporting Month February 2015 the progress showed signs of improvement progress in February 2015 is the best progress during Construction, if the Contractors can maintain the last progress in the following month, this sub-project could be finished as schedule. Shown in ANNEX P-4 Executive Summary Report are the current problem and actions to be taken to attain substantial progress in order to catch-up with the schedule. For contract packages under AWP-2 and AWP-3 which have a combined total of 17 Packages, a brief summary of the actual activities and status as of this reporting period are presented in Table 1.1, page 8 of this Report.