Monitoring Report of the LARAP Package No. 6

Western I ndonesia National Roads I mprovement Project 4-12 a Proposed to be replaced. C. Update during this reporting month of January 2015 a Nothing to report this period. b Proposed to be replaced.

10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam

Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of February 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko

Province : Bengkulu A. Previous Status : • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Monitoring Report for compensation payments of 81 out of 183 PAP have been submitted to World Bank. B. Pending Issues, Concern and Actions a Compensation payments for the remaining 51 PAP is in process and to be paid from 2015 National Budget. C. Update during this reporting month of February 2015 a The remaining 58 PAP s Monitoring Report for compensation already submitted to World Bank dated February 6, 2015.

12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura

Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. B. Pending Issues, Concern and Actions a No allocated budget to pay land acquisition in the 2014 budget of the Local Government. Compensation payments to be allocated from the 2015 budget. Western I ndonesia National Roads I mprovement Project 4-13 C. Update during this reporting month of February 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

13. Monitoring Report of the LARAP Package No. 13 : Sp. Rukis Tj. Kemuning

Province : Bengkulu A. Previous Status : • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. C. Update during this reporting month of February 2015 a Affected assets inventory and measurements is under process by BPNLand Acquisition Committee. b Land Appraisal procurement is under process.

14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang

Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on November 2014. • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. B. Pending Issues, Concern and Actions a LARAP implementation is scheduled on March 2015. C. Update during this reporting month of February 2015 a No update this period.

15. Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel

Province : Sumatera Utara A. Previous Status : • Revised LARAP documents was resubmitted to World Bank on January 30, 2014 • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • Appraisal result completed. B. Pending Issues, Concern and Actions a Negotiation with PAP on the remaining 16 out of the total 20 village is on going.. C. Update during this reporting month of February 2015