Technical Assistance for Capacity Building for Disaster Risks Reduction
4.2 Procurements
Procurement shall be conducted under the Bank s Procurement Procedures as mentioned in the Loan Agreement. The International Competitive Bidding ICB based on the Bank letter Ref. WINRIP136 will apply to the packages with the construction estimated cost more than US 25 Million to comply with the new Bank s threshold for ICB. According to the GOI regulation, a prequalification shall be applied for the packages with the construction estimated cost more than IDR 10 Billion. Review from previous procurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojects qualification still used Pre-Qualification and for remaining sub-project must be process with Post Qualification. As well as for all NCB the World Bank also requested to follow Post Qualification in procurement process. All subprojects for WP-1 have been started with prequalification since 30 December 2011 for ICB multiple contract. This was an advanced procurement action agreed by both DGH and the World Bank prior to the CTC establishment. All AWP-1 sub-projects had signed the contract. The last 2 sub-projects, Package 02: Pd. Sawah Simpang Empat and Package 03: Manggopoh Padang Sawah, signed the contract on December 6, 2013 and NOL for disbursement for all 4 packages had been issued by the World Bank on December 10, 2013. As of the reporting month February 2015, a more detailed current updates are fully indicated in Sub-Chapter 1.4 Procurement on Page 3 of this Report and consolidated project status in a tabulated format shown in Table 1.1 on page 8 of this Report. Under Category 3 of Loan Agreement there are three 3 consultancy packages namely ; 1. Capacity Building For Disaster Risks Reduction 2. Capacity Building For Environmental Management 3. Capacity Building For Road Safety Consultant for Capacity Building For Disaster Risks Reduction is still to be procured, while the other two 2 consultancy packages are proposed to be deleted.. A more detailed updates can be found in Sub- Chapter 1.5 Procurement on Page 7 of this Report. Documents of Request For Expression of Interest has been finalized by TLKJ. As of Reporting TLKJ is months, preparing Owner s Estimate for procurement process The WINRIP updated Procurement Plan is attached as Appendix F.4.3 Civil Works Implementation
All 4 contract packages under AWP-1 are currently under construction by different contractors. Commencement of works for all the 4 packages commenced on the 2 nd week of January 2014. As of to date, there are three 3 new sub-projects that were awarded to the winning bidders with the signing of Contract Agreements between the Government of Indonesia and the winning Contractors. Two 2 of the contract packages are under implementation schedule AWP-2 and the other contract package is under AWP-3.Parts
» WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» World Bank Implementation Review Mission and Site Visit
» Package 17 Sp. Gunung Kemala Pugung Tampak AWP-3.
» Package 11 Bantal Mukomuko AWP-2
» Package 13 Sp. Rukis Tj. Kemuning AWP-2
» Packages 5 Simpang Rampa Poriaha AWP-2
» Package No. 6 Pasar Pedati Kerkap AWP-2
» Package No.19 Lais Bintunan AWP-3 Package No.15 Sibolga Batas Tapsel AWP-3
» Technical Assistance for Capacity Building for Disaster Risk Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Consolidated Update of the Progress of the Project
» Background WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Project Development WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Project Objective WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» CTC Consultants WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» DSC Consultants WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Procurements WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Civil Works Progress WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 21.04 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 44.25 30.11 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» - 33.85 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Quality Assurance WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Monitoring of Environmental Aspects During Construction
» Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» External Monitoring Report SatkerPPK to BLH for Implementation of
» Monitoring Report of the LARAP Package No. 2 Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7 Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam
» Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko
» Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura
» Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20 : Lubuk Alung - Sicincin
» Monitoring Report of the LARAP Package No. 21 : Lubuk Alung - Kurataji
» Anti Corruption Issues WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Road Safety Audit WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» Letter Database System, used to record all information of incoming and
» Document Library System, used to record all information of document and
» World Bank and GOI Compliance
» Implementation Support Components WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Environmental and Social Impact Issues
» System Design Management Information System
» Project Risks and Mitigation Measures
» 0.29 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.82 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 2.88 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.65 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 3.00 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.94 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 2.20 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 4.86 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 2.16 1.91 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 35.31 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 47.72 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 65.59 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 84.21 100.00 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 4.69 2.95 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 3.530 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 3.95 - WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.06 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 7.877 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.77 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 20.359 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.96 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 44.25 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.61 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 1.03 - WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 8.04 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 5.95 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 24.30 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» 0.12 21.76 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» -14.27 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
» -11.88 WINRIP DOC MPR CTC MPR No.26 2015 02 2015 02 11 00224.
Show more