Western I ndonesia National Roads I mprovement Project 4-13 C. Update during this reporting month of February 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

13. Monitoring Report of the LARAP Package No. 13 : Sp. Rukis Tj. Kemuning

Province : Bengkulu A. Previous Status : • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. C. Update during this reporting month of February 2015 a Affected assets inventory and measurements is under process by BPNLand Acquisition Committee. b Land Appraisal procurement is under process.

14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang

Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on November 2014. • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. B. Pending Issues, Concern and Actions a LARAP implementation is scheduled on March 2015. C. Update during this reporting month of February 2015 a No update this period.

15. Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel

Province : Sumatera Utara A. Previous Status : • Revised LARAP documents was resubmitted to World Bank on January 30, 2014 • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • Appraisal result completed. B. Pending Issues, Concern and Actions a Negotiation with PAP on the remaining 16 out of the total 20 village is on going.. C. Update during this reporting month of February 2015 Western I ndonesia National Roads I mprovement Project 4-14 a Compensation payment for PAP in four 4 villages out of 20 Village is in process.

16. Monitoring Report of the LARAP Package No.16

: Seblat - Ipuh Province : Bengkulu A. Previous Status : • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30,2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation for the remaining 311 PAP out of 450 PAP have to be prepared and submitted for review and for submission to World Bank. b LARAP Implementation is underway for the remaining 311 PAP be allocated 2015 national budget C. Update during this reporting month of February 2015 a Monitoring Reports of the LARAP s implementation for the remaining 311 PAP out of 450 PAP already submitted to World Bank dated February 6, 2015.

17. Monitoring Report of the LARAP Package No.17

: Sp. Gunung Kemala Pg. Tampak Province : Lampung A. Previous Status : • CTC revised the LARAP documents taking into consideration all the Bank s comments and PMU resubmitted the documents to the World Bank on November 6, 2013 • World Bank approved the corrected LARAP documents on November 12, 2013 • Director of Planning issued letter on November 18, 2013 to the Director of Implementation Affairs to inform that World Bank had already approved the LARAP documents for implementation by the land acquisition committee. B. Pending Issues, Concern and Actions a PMU waiting report of the land acquisition progress result from Satker. C. Update during this reporting month of February 2015 a Appraisal of affected assets buildings, houses, plant and other obstructions by Independent Appraisal Team is on-going.

18. Monitoring Report of the LARAP Package No.18

: Mukomuko Bts. Sumbar Province : Bengkulu A. Previous Status : • Proposed to be replaced. B. Pending Issues, Concern and Actions a Proposed to be replaced. C. Update during this reporting month of February 2015