Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 44
6 PROJECT PERFORMANCE
6.1 World Bank and GOI Compliance
6.1.1 World Bank Missions
No World Bank implementation mission this period.
6.1.2 Agreed Key Actions and Mission Plans During Recent World Bank Visit
A project review meeting took place on July 16, 2014 in the Bina Marga office. The meeting was chaired by Mr. Agusta Sinulingga, the head of PMU WINRIP, and was attended by some
representatives of PMU, CTC s Team, and the Bank s Team.
It was understood that Bina Marga will propose another two packages to replace package 9 and package 18. The candidates of the replacement are in North Sumatera Province. PMU will visit the
site in North Sumatera in July 2014 and report to Bank on the condition of the replacement candidates.
A list of the key actions to be monitored during the next progress review meeting is listed below.
No. Action
By Whom Status and Target dates
1 Project reviews
DGH and Bank
August 2014 2
Review revised version of the ToR for Capacity Enhancement on Disaster Risk Mitigation and
translate into English PMU and
CTC Will be a meeting between TLKJ
and WB on July 23, 2014
3 Complete and send to the Bank:
- AMDAL for packages 7, 11, 12, 14, 16 and UKL- UPL package 13
CTC •
11, 16, 13 have been sent formally to Bank
need NOL from WB
• 7, 12, 14 have been sent
informally to Bank need
comment 4
Complete and send to the Bank UKL UPL for package 4
CTC •
Will be submitted from Balai to PMU in August, 2014
• Will be submitted to Bank on
September 2014
5 Submit LARAP documents for packages 7, 8, 10
and 12 for Bank review DGH
• 8, 10 submitted in End of July,
2014 •
7, 12 will be submitted in end of August
6 Submit to the Bank the LARAP monitoring
report for package 2 PMU
Will be submitted on August, 2014
7 Submit to the Bank the LARAP monitoring
reports for packages 6, 11 and 19 PMU
Will be submitted on August 2014
8 Submit to the Bank the LARAP monitoring
PMU Will be submitted on December
2014
Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 45
No. Action
By Whom Status and Target dates
report for packages 13 and 15 9
Submit to the Bank the LARAP for packages 14, 20 and 21
PMU Will be submitted on October 2014
10 Submit to the Bank the LARAP monitoring
report for package 17 PMU
Will be submitted on September 2014
11 Complete NCB standard bidding documents
after based on the discussion with the Bank on June 11
MPW Bintek
and Pusdata
and Bank Bank will send comments on July
22, 2014
12 BD for Package 17 was issued to the
prequalified bidder. PMU
The deadline of bid submission is on August 15, 2014
13 Submit to the Bank the revised AER for package
5 PMU
NOL has been sent 14
Submit to the Bank the revised AER for packages 11 and 13
PMU NOL has been sent
15 Submit bidding document for package 11 and
13 to the Bank PMU
Comment from Bank to the informal submission will be sent on
July 21, 2014. BD for package 11 and 13 will be submitted formally
to the Bank on July 22, 2014
16 Accelerate Engineering Estimate approval for
package 15 and submit the respective bidding document to the Bank
PMU SBD 15 will be sent to bank on
July 222014
17 Update procurement plan and submit to the
Bank for its prior review PMU
Will be submitted to Bank on July 21, 2014
18 Submit to the Bank the auditing report of the
2012 and 2013 financial statements PMU
Has been sent to Bank
19 Submit to the Bank the revised PMM, including
the web application and the revised Complaint Handling Mechanism
PMU The
revised PMM
will be
submitted on August 15, 2014. CHM is available online at WINRIP
website
20 Finalize ToR for technical and financial audit
and submit proposal to DFAT for funding DGH
team leader for
EINRIP and Bank
A meeting will be scheduled in the middle of August
21 Make sure that adequate budgets for LARAP
implementation are allocated in 2015 for packages 14, 16, 20 and 21
DGH Will
be checked
to Local
Government of West Sumatera and Balai III for 16
22 Submit additional LARAPs for packages 2
Padang Sawah Simpang Empat see Annex 5
DGH Submitted to Bank on July 16, 2014
Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 46
No. Action
By Whom Status and Target dates
23 DSC to inform the PMU and the Bank about the
deadlines for engineering design and reviewapproval of slope protection design
completion and the nomination of the chief inspector for package 4
DSC Will be discussed with new TL of
DSC and will report to Bank promptly Early August, 2014
24 Organize training on anti-corruption for the
TPM team and CRO CTC
Done 25
Carry out environment and social management training for DSC field engineersstaff of
contractors CTC
Done 26
Finalize the information exchange protocols from SIPP Terpadu to the WINRIP Project Portal
DGH Done
6.1.3 Performance Indicators
GOI and the World Bank have agreed on a set of Key Performance Indicators KPIs to measure the
project s performance in achieving its stated development objectives. These KPIs are provided in the World Bank s Project Appraisal Document PAD, together with baseline data and targets.
The annual targets for KPIs that are indicated in the Project Appraisal Document are based on the
initial Project Implementation Schedule as shown in Appendix I.
The CTC is concentrating on the establishment of precise definitions, calculation methods and data collection procedures to monitor the KPIs.
6.2 Implementation Support Components
6.2.1 Core Team Consultant CTC
The CTC is responsible to provide support to the PMU and DGH in the management of the Project, based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, information
management and dissemination, quality assurance and performance review for the Design and Supervision Consultants DSC, implementation and monitoring of the anti-corruption action plan,
support for project monitoring and evaluation, and support for implementation of a training program to support project management and implementation.
The CTC contract No. 06-20CTCTALN80431112 was signed on 5 November 2012 by both DGH and a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. Epadascon
Permata Engineering Consultant.
The main CTC activities during July 2014 are as follows: •
Continue assistance to PMU as and when required.