Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 56
6.5 Road Safety Audit
6.5.1 Activities During This Month July 2014
There are two activities during this month, i.e: 1. Desk study for Road Safety Audit at detailed design stage for Package 16 Seblat Ipuh,
2. Site Visit to Sibolga for preliminary and reconnaissance survey of the new package replacement road. The two roads that have been visited are : i Sibolga
Padang Sidempuan, and ; ii Sibolga Barus. The two road that has to be replaced are : i Package 18 Mukomuko Batas Sumbar, and;
ii Package 9 Rantau Tijang Kota Agung.
6.5.2 Current status of the project for technical field as of July 2014.
The Details of Progress of Technical Design Review and Road Safety Audit as of the end of July 2014
is as shown in the tabulated format and included as Appendix B.
Technical Design Review Road Safety Audit Report Status
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Road Safety Audit
Report By BINTEK
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
AWP -2
5 Sp.Rampa
Poriaha Link No.015.xx
completed completed completed completed
- Final Technical Report is resubmitted
on 17th September 2013 6
PS.Pedati - Kerkap Link No.010.0
completed completed completed completed
- Final Technical Report is submitted
on 17th September 2013 7
Indrapura Tapan
Link No.019.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Reviewed and
prepared by Sub Directorate of EA RS
• Final
Technical Advisory
is submitted on 5th February 2013
• Final RSA Report is submitted on
May 2014 8
Bts.Pariaman Manggopoh
Link No.024.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Reviewed and
prepared by Sub Directorate of EA RS
• Final
Technical Advisory
is submitted on 5th February 2013
• Final RSA Report is submitted on
May 2014 9
Rantau Tijang Kota
Agung Link No.026.1
By DSC By DSC
By DSC -
- -
10 Sp.Empat Sp. Air
Balam Link No.034.1
- By DSC
- By DSC
- By DSC
Technical Advisory
Reviewed and prepared by Sub
Directorate of EA RS •
Final Technical
Advisory is
submitted on 5th February 2013 •
Final RSA Report is submitted on May 2014
11 Bantal - Mukomuko
Link No.015.2 completed completed completed
completed -
Final Technical Report is resubmitted on 16th August 2013
12 Kambang
Indrapura Link No.017.2
- By DSC
- By DSC
- By DSC
Technical Advisory
Reviewed and prepared by Sub
Directorate of EA RS •
Final Technical
Advisory is
submitted on 5th February 2013 •
Final RSA Report is submitted on May 2014
13 SP.Rukis - TJ.Kemuning
Link No.006.0 completed completed completed
completed -
Final Technical Report is resubmitted on 16th August 2013
AWP -3
14 Painan
Kambang Link No.017.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 28 May 2014
15 Sibolga
Bts TapSel Link No.016.1
completed completed completed completed
- Final Technical Report is submitted
on 23th September 2013 16
Seblat Ipuh
Link No.010.0 -
By DSC -
By DSC -
By DSC Technical
Advisory -
DSC resubmitted to CTC Drawings on June 25, 2014 for further review.
17 Sp.Gng Kemala
Pg.Tampak Link No.061.1
PPC-TA WINRIP
PPC-TA WINRIP
PPC-TA WINRIP
- -
-
Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 57
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Road Safety Audit
Report By BINTEK
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
18 Mukomuko
Bts.Sumbar Link No.015.3
By DSC By DSC
By DSC -
- -
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed -
Final Technical Report is submitted on 17th September 2013
20 Lubuk Alung
Sicincin Link No.009.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 23 May 2014
21 Lubuk Alung
Kuraitaji Link No.009.1
By DSC By DSC
By DSC Technical
Advisory -
Final Technical Advisory is submitted on 23 May 2014
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui
Biha Social Issues:
Existing mosque is partially traversed due widening of the existing travelledway. Due to resistance to partially demolished and rebuild the mosque, a new action plan is proposed,
where the road alignment centerline will be shifted to the other side. Land acquisition is required on the other side of the road centerline alignment if the new action
plan push through.
Environmental Issues:
CTC have reviewed and gave comments on RKPPL that was submitted by the Contractor. Contractor still to resubmitted the revised RKPPL.
CTC to check if the DSC and Contractor implement the requirements and recommendations in the AMDAL on the site and incorporated in the design. CTC is waiting for the submission of AMDAL
drawings recommendations from DSCContractors.
6.6.2 Package No.02: Padang Sawah
Simpang Empat Social Issues:
Remaining twenty one 21 affected persons and twenty four 24 new PAP are not yet compensated by the Local Government. Five 5 of the twenty one 21 affected persons are
residing along the proposed bridge site of Air Gadang Bridge. Documents for compensation payments are being processed by the Local Government.
Monitoring Report concerning the payments to the remaining affected peoples still to be prepared for submission to World Bank.
Environmental Issues:
RKPPL submitted by Contractor under review by CTCSubdit TLKJ. CTC need to check the recommendation UKLUPL bridge in the field for clearance of
environmental issues which have to be integrated in to the design.