Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 21 Procurement details of the above mentioned sub-projects and updates are fully described in Sub Chapter 1.4 Procurement on page 3 of this Report. Under Category 3 of Loan Agreement there are three 3 consultancy packages namely ; 1. Capacity Building For Disaster Risks Reduction 2. Capacity Building For Environmental Management 3. Capacity Building For Road Safety Consultant for the three 3 consultancy packages are still to be procured. Draft Terms of References for the three packages are in the process of finalization. The WINRIP updated Procurement Plan is attached as Appendix F.

4.3 Civil Works Implementation

All 4 contract packages under AWP-1 are currently under construction by different contractors. Commencement of works for all the 4 packages commenced on the 2 nd week of January 2014. Table 4.1 shows the details for each contract packages. Table 4.1 Program Contract Package Contractor Name of Road Province Contract Signed Notice to Proceed Contract Time Completion Date AWP-1 1 Jaya Konstruksi Manggala Pratama Tbk Biha - Krui Lampung Nov 25, 2013 Jan 8, 2014 640 CD Oct 9, 2015 2 Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp. Empat including Air Gadang West Sumatera Dec 6, 2013 Jan 6, 2014 730 CD Jan 5, 2016 3 Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah West Sumatera Dec 6, 2013 Jan 6, 2014 730 CD Jan 5, 2016 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal Bengkulu Nov 14, 2013 Jan 10, 2014 730 CD Jan 9, 2016

4.4 Civil Works Progress

As of the end of this reporting month, all the 4 contractors are about to complete their mobilization and construction of Base Camps in all packages have been completed. Other activities done during this month were setting up of laboratory testing building, staking out and repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates and other Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 22 minor works. Progress status of the four 4 on-going civil work contract as of this reporting period are shown in Table 4.2. Table 4.2 Program Contract Package Contractor Name of Road Target Progress Schedule Ending July 2014 Actual Progress Accomplished Slippage Time Elapsed AWP-1 1 Jaya Konstruksi Manggala Pratama Tbk Biha - Krui

24.50 4.79

- 19.71 32.03 2 Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp.Empat incl.Air Gadang Brd

17.48 9.69

- 7.79 28.36 3 Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah

10.70 7.60

- 3.10 28.36 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal 12.85

0.87 - 11.98

27.81 As expected due to the fasting period and the long holidays during the month of July 2014, the cummulative work progress of the four 4 on-going Construction packages failed to gain any substantial accomplishments to reduce the negative slippages. At the end of this reporting month of July 2014, all the four 4 contract packages were all lagging behind schedule. The situation remains the same as in previous month as all the contract packages continue to follow a downward trend of delayed schedules. Packages No. 1 : Biha Krui Based on previous month s figures, the negative slippage or delayed works further slipped down to -19,71 against -14,35 in June 2014. At the current rate of progress since the works started in January 8, 2014 which is only 4,79 to date, or a miniscule monthly work progress of 0,68 per- month, the project will never be completed on the target date of completion on October 9, 2015. Unless a realistic workable action plan and catch up schedule is implemented by the Contractor, the work delays will keep on accumulating. Packages No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge The previous month s percentage of delayed works of -4,82 which was still at manageable stage also incurred downward trend of negative slippage of -7.80 this end of month. The DSC Team leader issued a letter to the Contractor wherein various recommendation were suggested to the Contractor to implement in order to catch up with the work schedule. In addition the issued letter served as first warning to the Contractor that unless there are valid reasons for the delay, sanctions in accordance with the Contract will be recommended against the Contractor. Package No. 3 : Manggopoh Padang Sawah Although the current slippage of -3.10 this month, the delayed works is also leading to a