Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 58
6.6.3 Package No.03: Manggopoh
Padang Sawah Social Issues:
Documents for compensation payments for the remaining five 5 affected persons processed and resolve by the Local Government.
Monitoring Report concerning compensation payments to the five 5 remaining affected persons still to be prepared for submission to World Bank.
Environmental Issues:
RKPPL submitted by Contractor under review by CTCSubdit TLKJ.
6.6.4 Package No.04: Ipuh
Bantal Social Issues:
No more issue and concern Environmental Issues:
CTC carried out training of RKPPL for DSC and Contractor staff on July 7, 2014. CTC to assist the BALAI locally hired consultant to decide the sampling locations and
environmental mitigation of project. The locally hired consultant have already conducted sampling on July 7 to 11, 2014 and UKL and UPL reports are under preparation for submission.
6.6.5 Package No.05: Sp. Rampa
Poriaha Social Issues:
PMUCTC is awaiting the LARAP implementation Report Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.6 Package No.06: Psr.Pedati
Kerkap Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.7 Package No.07: Indrapura
Tapan Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank.
Environmental Issues:
Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 59
CTC need to check the recommendation of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
CTC informally submitted to the World Bank the AMDAL documents from the Subdit TLKJAMDAL local consultant hired by BALAI.
6.6.8 Package No.08: Bts Kota Pariaman
Manggopoh Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank for NOL.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.9 Package No.09: Rantau Tijang
Kota Agung Social Issues:
Still no issues and concerns. Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.10 Package No.10: Sp. Empat
Air Balam Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank for NOL.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.11 Package No.11: Bantal - Mukomuko
Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.