Activities During This Month July 2014 Current status of the project for technical field as of July 2014.

Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 58

6.6.3 Package No.03: Manggopoh

Padang Sawah Social Issues:  Documents for compensation payments for the remaining five 5 affected persons processed and resolve by the Local Government.  Monitoring Report concerning compensation payments to the five 5 remaining affected persons still to be prepared for submission to World Bank. Environmental Issues:  RKPPL submitted by Contractor under review by CTCSubdit TLKJ.

6.6.4 Package No.04: Ipuh

Bantal Social Issues:  No more issue and concern Environmental Issues:  CTC carried out training of RKPPL for DSC and Contractor staff on July 7, 2014.  CTC to assist the BALAI locally hired consultant to decide the sampling locations and environmental mitigation of project. The locally hired consultant have already conducted sampling on July 7 to 11, 2014 and UKL and UPL reports are under preparation for submission.

6.6.5 Package No.05: Sp. Rampa

Poriaha Social Issues:  PMUCTC is awaiting the LARAP implementation Report Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.6 Package No.06: Psr.Pedati

Kerkap Social Issues:  Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.7 Package No.07: Indrapura

Tapan Social Issues:  Corrected LARAP documents still to be submitted for final review prior to submission to World Bank. Environmental Issues: Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 59  CTC need to check the recommendation of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.  CTC informally submitted to the World Bank the AMDAL documents from the Subdit TLKJAMDAL local consultant hired by BALAI.

6.6.8 Package No.08: Bts Kota Pariaman

Manggopoh Social Issues:  Corrected LARAP documents still to be submitted for final review prior to submission to World Bank for NOL. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.9 Package No.09: Rantau Tijang

Kota Agung Social Issues:  Still no issues and concerns. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.10 Package No.10: Sp. Empat

Air Balam Social Issues:  Corrected LARAP documents still to be submitted for final review prior to submission to World Bank for NOL. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.11 Package No.11: Bantal - Mukomuko

Social Issues:  Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.