Visit WINRIP DOC MPR CTC MPR No.19 2014 07 2014 07 10 00224.
Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 5
the II Eleven contractors who passed the qualification criteria are eligible to be invited to submit their respective tenders.
During this month, the Director of Planning DGH-BIPRAM resubmitted the Revised Application Evaluation Report AER to the World Bank requesting Bank s concurrence
and issuance of No Objection Letter NOL.
The six 6 issues and queries raised by the Bank on the previous submittal were all addressed by CTC in coordination with POKJA and incorporated in the Revised AER.
Based on the final review by the Bank, there were still some minor comments on the submitted documents that are to be rectified.
However, since the comments were minor in nature and in no way will alter or affect the outcome of the evaluation, the Bank provisionally accepted the Report and
interpose No Objection on DGH-BIPRAM recommendation to prequalify eleven 11 out of fourteen 14 applicant
bidders, but subject to rectifying the AER by incorporating the Bank s minor comments.
With the Bank s conditional acceptance of the Revised AER, DGH-BIPRAM endorsed the Bank s letter of No Objection to the Director of Implementation Affairs Region I for
further action on the procurement activities.
Following are the eleven 11 prequalified applicant bidders :
1. PT. Adhi Karya Persero, Tbk Indonesia 2. PT. Bangun Cipta Kontraktor Indonesia
3. PT. Brantas Abipraya Persero Indonesia 4. PT. Hutama Karya Persero
PT. Seneca Indonesia JO Indonesia 5. PT. Multi Structure Indonesia
6. PT. Nindya Karya Persero Indonesia 7. PT. Nusa Konstruksi Enjiniring, Tbk Indonesia
8. PT. Pembangunan Perusahaan Persero Indonesia 9. PT. Waskita Karya Persero, Tbk Indonesia
10. PT. WIdya Sapta Colas Indonesia 11. PT. Yasa Patria Perkasa Indonesia
Draft Bidding Documents for International Competitive Bidding ICB were forwarded to the World Bank by DGH-BIPRAM with request for Bank s issuance of No Objection Letter
NOL.
Draft Bidding Documents were concurred by World Bank on July 22, 2014 with the issuance of No Objection Letter NOL to issue the documents to all the prequalified
applicant-bidders.
DGH-BIPRAM forwarded the Bank s NOL to Balai for further action and proceed with the bidding.
Notification of Prequalification Results were issued on July 21, 2014 to all the fourteen 14 applicant-bidders who submitted prequalification documents.