Package No.07: Indrapura Environmental and Social Impact Issues

Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 60

6.6.12 Package No12: Kambang

Indrapura Social Issues:  Corrected LARAP documents still to be submitted for final review prior to submission to World Bank for NOL Environmental Issues:  CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental issues which integrated in to the design.  CTC had submitted informally to the World Bank on June 30, 2014 AMDAL Doc from the Subdit TLKJ AMDAL Consultant.

6.6.13 Package No.13: Sp. Rukis

Tj. Kemuning Social Issues:  Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.14 Package No.14: Painan

Kambang Social Issues:  Corrected LARAP documents still to be submitted to World Bank for NOL. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.  CTC had submitted informally to the World Bank on June 30, 2014 AMDAL Doc from the Subdit TLKJ AMDAL Consultant

6.6.15 Package No.15: Sibolga

Bts. Tapsel Social Issues:  LARAP implementation Monitoring Report from SatkerPPK still to be submitted to PMUCTC for review and for submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.16 Package No.16: Sebelat

Ipuh Social Issues:  Monitoring Reports of the LARAP s implementation have to be prepared and submitted for Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 61 review and for submission to World Bank.  LARAP documents for this Package No.16 covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents to need be prepared. Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.17 Package No.17: SP. Gunung Kemala

Pg. Tampak Social Issues:  LARAP implementation report is not yet submitted to PMUCTC. Environmental Issues:  CTC need to check the recommendations of AMDAL UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.18 Package No.18: Mukomuko

Bts. Sumbar Social Issues:  Still no issues and concerns Environmental Issues:  CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.19 Package No.19: Lais - Bintunan

Social Issues:  Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. Environmental Issues:-  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.

6.6.20 Package No.20: Lubuk Alung

Sicincin Social Issues:  Corrected LARAP documents still to be submitted for final review prior to submission to World Bank. Environmental Issues:  CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.