Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 60
6.6.12 Package No12: Kambang
Indrapura Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank for NOL
Environmental Issues:
CTC need tocheck the recommendations of AMDAL in the field for clearance of environmental issues which integrated in to the design.
CTC had submitted informally to the World Bank on June 30, 2014 AMDAL Doc from the Subdit TLKJ AMDAL Consultant.
6.6.13 Package No.13: Sp. Rukis
Tj. Kemuning Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.14 Package No.14: Painan
Kambang Social Issues:
Corrected LARAP documents still to be submitted to World Bank for NOL.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
CTC had submitted informally to the World Bank on June 30, 2014 AMDAL Doc from the Subdit TLKJ AMDAL Consultant
6.6.15 Package No.15: Sibolga
Bts. Tapsel Social Issues:
LARAP implementation Monitoring Report from SatkerPPK still to be submitted to PMUCTC for review and for submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.16 Package No.16: Sebelat
Ipuh Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for
Monthly Progress Report July 2014
Western I ndonesia National Roads I mprovement Project 61
review and for submission to World Bank. LARAP documents for this Package No.16 covers only land acquisition for the road link. If there
are land acquisition for the bridge site, a separate LARAP documents to need be prepared.
Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.17 Package No.17: SP. Gunung Kemala
Pg. Tampak Social Issues:
LARAP implementation report is not yet submitted to PMUCTC. Environmental Issues:
CTC need to check the recommendations of AMDAL UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.18 Package No.18: Mukomuko
Bts. Sumbar Social Issues:
Still no issues and concerns Environmental Issues:
CTC need to check the recommendations of AMDAL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.19 Package No.19: Lais - Bintunan
Social Issues:
Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank.
Environmental Issues:-
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.
6.6.20 Package No.20: Lubuk Alung
Sicincin Social Issues:
Corrected LARAP documents still to be submitted for final review prior to submission to World Bank.
Environmental Issues:
CTC need to check the recommendations of UKLUPL in the field for clearance of environmental issues which will be integrated in to the design.