Procurement WINRIP DOC MPR CTC MPR No.19 2014 07 2014 07 10 00224.

Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 5 the II Eleven contractors who passed the qualification criteria are eligible to be invited to submit their respective tenders. During this month, the Director of Planning DGH-BIPRAM resubmitted the Revised Application Evaluation Report AER to the World Bank requesting Bank s concurrence and issuance of No Objection Letter NOL. The six 6 issues and queries raised by the Bank on the previous submittal were all addressed by CTC in coordination with POKJA and incorporated in the Revised AER. Based on the final review by the Bank, there were still some minor comments on the submitted documents that are to be rectified. However, since the comments were minor in nature and in no way will alter or affect the outcome of the evaluation, the Bank provisionally accepted the Report and interpose No Objection on DGH-BIPRAM recommendation to prequalify eleven 11 out of fourteen 14 applicant bidders, but subject to rectifying the AER by incorporating the Bank s minor comments. With the Bank s conditional acceptance of the Revised AER, DGH-BIPRAM endorsed the Bank s letter of No Objection to the Director of Implementation Affairs Region I for further action on the procurement activities. Following are the eleven 11 prequalified applicant bidders : 1. PT. Adhi Karya Persero, Tbk Indonesia 2. PT. Bangun Cipta Kontraktor Indonesia 3. PT. Brantas Abipraya Persero Indonesia 4. PT. Hutama Karya Persero PT. Seneca Indonesia JO Indonesia 5. PT. Multi Structure Indonesia 6. PT. Nindya Karya Persero Indonesia 7. PT. Nusa Konstruksi Enjiniring, Tbk Indonesia 8. PT. Pembangunan Perusahaan Persero Indonesia 9. PT. Waskita Karya Persero, Tbk Indonesia 10. PT. WIdya Sapta Colas Indonesia 11. PT. Yasa Patria Perkasa Indonesia Draft Bidding Documents for International Competitive Bidding ICB were forwarded to the World Bank by DGH-BIPRAM with request for Bank s issuance of No Objection Letter NOL. Draft Bidding Documents were concurred by World Bank on July 22, 2014 with the issuance of No Objection Letter NOL to issue the documents to all the prequalified applicant-bidders. DGH-BIPRAM forwarded the Bank s NOL to Balai for further action and proceed with the bidding. Notification of Prequalification Results were issued on July 21, 2014 to all the fourteen 14 applicant-bidders who submitted prequalification documents. Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 6 5. Bid Documents for National Competitive Bidding The Director Planning DGH-BIPRAM submitted to World Bank the Draft Standard Bidding Documents SBD for National Competitive Bidding requesting for Bank s final review and issuance of No Objection Letter NOL. Based on Bank s review of the documents, comments were provided directly on the soft file for incorporation in the final edition of the bid documents Subject to incorporation of all the Bank s comments, the Bank conditionally interpose No Objection to the Standard Bidding Documents for procurement of Works for National Competitive Bidding NCB Method.

1.5 Consolidated Update of the Progress of the Project

Other brief updates of the pre-construction activities of this reporting month are shown in Table 1.1. Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 7 Consolidated Project Status As Of End July 2014 Table 1.1 Length Width Estimated Cost PIP Mar 2012 Excl. VAT DED Technical Design Review Road Safety Audit Km m IDR Milion Status Doc Requirement Status Doc Requirement Status Budget Allocation Status Estd. Start Duration Months 1 Krui - Bha 25 7 146,668.00 Completed Completed Completed SPPL AMDAL No.1 17 SPPL OK P2JN 2010 AMDAL Subdit TLKJ OK 2012 1.LARAP 2.Lap.Mon LARAP 1.NOL WB 4 Jan 13 2.NOL WB Satker PJN Prop 98 Completed Jan-14 24.00 A Padang Sawah - Sp. Ampat 40.9 7 Including Air Gadang Bridge 100 m 7 3 Manggopoh - Padang Sawah 32 7 152,434.90 Completed Completed Completed SPPL OK P2JN 2010 1.LARAP 2.Monit. LARAP Report 1.NOL WB 13 Dec 12 2.Process APBD Propinsi 99 Completed Jan-14 24.00 A 4 Ipuh - Bantal 42.4 7 226,275.10 Completed Completed Completed SPPL UKLUPL SPPL OK P2JN 2010 UKL?UPL under preparation by local consultant. Consultant meeting w ith CTC 7 Aug, 2014 1.LARAP 2.Monit. LARAP Report 1.NOL WB 10 Dec 12 2.Completed Satker PJN Propinsi 100 Completed Jan-14 24.00 A 5 Sp. Rampa - Poriaha 11.1 6 55,126.60 Completed Completed Completed UKLUPL OK Balai 1 2011 1.SLARAP 2.LARAP monit Report 1.Nol WB 10 Dec 12 2.relocation 1 kiosk affected project w ill be done paralel construction Satker PJN Propinsi On Going Des-14 18.00 G 6 Ps. Pedati - Kerkap 25 7 72,018.80 Completed Completed Completed UKLUPL OK TLKJ 2011 1.SLARAP 2.LARAP monit Report 1.NOL WB 20 Nov 2013 2. Target of Larap Implementation is August 2014 Satker PJN Propinsi Compensati on payment in process Not Yet Started Dec-14 18.00 D 7 Indrapura - Tapan 19.5 7 96,921.00 Completed Completed Completed AMDAL OK TLKJ 2014 SLARAP Target July 2014 APBD Propinsi Target Mon: Oct 2014 Not Yet Started Jan-15 21.00 K 8 Bts. Kota Pariaman - Manggopoh 46.8 7 183,268.80 Completed Completed Completed AMDAL OK TLKJ 2013 LARAP Target LARAP July 2014 APBD Propinsi Target Mon: Oct 2014 Not Yet Started Feb-15 24.00 K 9 Rantau Tijang - Kota Agung 42 7 149,831.50 UKLUPL OK TLKJ 2011 LARAP Being prepared by Consultant recuirement Balai 3 Satker PJN Propinsi Not Yet Started Jun-15 21.00 H 10 Sp. Empat - Sp. Air Balam 61.7 7 241,617.20 Completed Completed Completed AMDAL OK TLKJ 2013 LARAP Target July 2014 APBD Propinsi Target Mon: Oct 2014 Not Yet Started Feb-14 24.00 K 11 Bantal - Mukomuko 50.1 6 157,820.00 Completed Completed Completed AMDAL OK TLKJ 2014 1.LARAP 2.LARAP monit Report 1.Nol WB :20 Nov 2013 2.Target August 2014 Satker PJN Propinsi 10 On Going Dec-14 24.00 G 12 Kambang - Indrapura 55.2 6 171,948.00 Completed Completed Completed AMDAL OK TLKJ 2014 SLARAP Target July 2014 APBD Propinsi Staking Out Not Yet Started Feb-15 24.00 K 13 Sp. Rukis - Tj.Kemuning 56.3 7 225,481.50 Completed Completed Completed UKLUPL OK P2JN 2011 1.LARAP 2.LARAP monit Report 1.NOL WB:20 Nov 2013 2.Target Dec 2014 Satker PJN Propinsi Compensati on payment in process On Going Dec-14 21.00 G 14 Painan - Kambang 31.5 7 118,993.00 On Going AMDAL OK TLKJ 2014 SLARAP Consultant recuirement Balai 2 APBD Propinsi Staking Out Not Yet Started Mar-15 21.00 C 15 Sibolga - Bts.Tap Sel 36 7 129,228.00 Completed Completed Completed UKLUPL OK Balai 1 2011 1.LARAP 2.LARAP monit Report 1.NOL WB:5Feb 2014 2.Target Dec 2014 Satker PJN Propinsi Inventory Not Yet Started Feb-14 21.00 D Seblat - Ipuh including 34.5 6 Air Lalang Air Guntung Bridge 64 m 6 18 Mukomuko - Bts.Sumbar 25.8 6 69,233.00 UKLUPL OK TLKJ 2011 SLARAP Being prepared by Consultant recuirement Balai 3 Satker PJN Propinsi Not Yet Started May-15 18.00 H 19 Lais - Bintuan 11.6 7 37,558.00 Completed Completed Completed UKLUPL OK TLKJ 2011 1.LARAP 2.LARAP monit Report 1.Nol WB :20 Nov 2013 2.Target August 2014 Satker PJN Propinsi Compensati on payment in process Not Yet Started Dec-15 18.00 D 20 Lubuk Alung - Sicincin 14.6 7 54,557.00 On Going UKLUPL OK TLKJ 2011 SLARAP Revision by Consultant recuirement Balai 2 Satker PJN Propinsi Staking Out Not Yet Started Feb-15 18.00 F 21 Lubuk Alung - Kurajati 16.8 7 65,788.00 On Going UKLUPL OK TLKJ 2011 SLARAP Revision by Consultant recuirement Balai 2 Satker PJN Propinsi Staking Out Not Yet Started Feb-15 18.00 F 2,776,633.60 Remarks : A On going Construction = 3 Packages in 1 study AMDAL West Sumatera Province B Revised Application Evaluation Report AER for submission to WB C Detailed Engineering Design Still to be prepared = 2 Packages in 1 study AMDAL Bengkulu Province D Procurement Preparation Underway - Standar Bidding Documents SBD and Owners Estimate OE are under finalization. E DEDRSA under review by Directorate of Technical Affairs F Technical Design Review is on-going G Revised Application Evaluation Report AER No Objection Letter NOL Issued by WB H Propose to be replaced by tw o 2 road links North Sumatera I Under Tendering Period K DSC Submitted Final Draw ings Group Pack. No. Procurement Status AWP-1 1.LARAP 2.Monit. LARAP Report 1.NOL WB 13 Dec 12 2.Pending Compensation for the remaining 21 PAP and additional 24 PAP APBD Propinsi 80 Completed Jan-14 AWP-2 Remarks Contract Implementation Plan Loan Package Name 2 207,390.20 Completed Completed Completed SPPLUKL UPL Bridge OK P2JN 2010 Environmental Social Land Acquisition 24.00 A I C AWP-3 Inventory On Going Dec-14 21.00 OK TLKJ 2011 1.LARAP 2.LARAP monit Report 1.NOL WB: 16 Sep 2014 2.Target Dec 2014 16 110,237.00 On Going 17 Sp.Gunung Kemala - Pg.Tampak 21.00 Mar-15 Not Yet Started Staking Out Satker PJN Propinsi 36.8 6 Satker PJN Propinsi OK TLKJ 2014 AMDAL Completed AMDAL No.1 17 1.NOL WB: 20 Nov 2014 2.Target Dec 2014 1.LARAP 2.LARAP monit Report 104,238.00 Completed Completed Monthly Progress Report July 2014 Western I ndonesia National Roads I mprovement Project 8 2 PROJECT DESCRIPTION

2.1 Background

The Government of Indonesia wishes to continue strengthening of the National Road system in Indonesia while the Eastern Indonesia National Roads Improvement Project EINRIP which is assisted by AusAID through the Australian Indonesia Partnership or AIP, is providing support program of National road and bridge improvement works in Eastern Indonesia. The Western Indonesia National Road Improvement Project WINRIP will provide similar support for National road and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roads administered directly by the National Government, including those currently classified as Provincial, Kabupaten District or non- status roads which are in process of being reclassified as National roads. In addition, provision will be made for major bridge repair works, rehabilitation, duplication and replacement as necessary to complement road betterment works.

2.2 Project Development

The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in the following detail. Key Project Data WINRIP Loan No. 8043-ID Project Cost US350 million Original Loan Amount US250 million Revised Loan Amount NA Board Approval Date 26 May 2011 Loan Signing Date 14 December 2011 Effectiveness Date 12 March 2012 Disbursement as of 31 December 2013 US 2.2 million 0.88 Original Closing Date 31 December 2017 Environmental Category B-Partial Assessment The IBRD loan amount is US250 million. The Project is intended to finance a part of the DGH investment program for national roads with a particular focus on the Western corridor of Sumatera. The corridor is one of the three main corridors in Sumatera and connects the city of Padang with a population of around one million to major towns along the west coast Bukittinggi, Sibolga and Bengkulu. It also connects through connector roads on the West coast to Medan in the northeast and to Pekanbaru in the centre of the island. The project has four components: Project Component 1: Betterment and Capacity Expansion of National Roads According to the Loan Agreement, this component will cover three work programs of betterment and capacity expansion of approximately 715.6 km including replacement of 194 meters of bridges. This civil works program will be executed in three Annual Work ProgramsAWP, as summarized in Table 2.1. The table shows the IBRD assisted scope and costs of civil works at estimated current