CTC Manning CTC Consultants

Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 15 International experts Senior Highway Engineer and Senior Road Safety Audit Engineer have completed their allocated man-months in the original contract and the contract Amendment No.1. DGH requested them to continue their assignment with the additional man-months to be included in the proposed Amendment No.2. In parallel with the instruction to speed up the process, detailed engineering design DED of some subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. The CTC has been instructed by DGH to review the DED of seven packages completed by the P2JNs package 5, 6, 11, 13, 15, 17 and 19. These conditions imply to the need of changing the CTC scope of works which will be included in CTC contract amendment and the need to extend the Senior Highway Engineer and Road Safety assignment.

3.1.3 CTC Contract

The CTC contract for “Western Indonesia National Roads Improvement Project” Contract No.06-20CTCTALN80431112 was signed on 05 November 2012. The contract is between the Government of Indonesia represented by Directorate General of Highways in the Ministry of Public Works and PT. Perentjana Djaja in joint venture with Yongma Engineering Co.Ltd. and PT. Epadascon Permata Engineering Consultant. The notice to proceed was issued by letter dated 6 November 2012 from the PPK, and the official starting date of the contract was set at 6 November 2012. Likewise, Amendment No. 1 to the original contract was signed on 25 October 2013 to cover all requirements of the CTC at present which are summarized below. • Replacement of the Senior Procurement Specialist • Extending the assignment of the Senior Highway Engineer. • Extending the assignment of the Senior Road Safety Audit Engineer. • Extending the assignment of the Procurement Specialist 2 and replacement of the Procurement Specialist 1. • Adding the new position of Bridge Engineer. • Adding the new position of Training Specialist, and • Adding the new position of Road Safety Engineer. Draft Amendment No. 2 is under preparation for submission and discussion with PMU. Proposed amendment to the Original Contract and Amendment No. 1 are additional man- months for professional and technical staff for international and local, replacement of foreign and local consultants and modification to various reinbursables to match with the actual requirements. Presented in Table 3.2 is the current status of CTC contract. Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 16 Table 3.2 Form of Currency USD IDR Original Contract + 10 VAT 1,404,370 23,556,940,000 Amendment No. 1 Exc VAT 1,315,925 22,426,175,000 VAT 10 131,592 2,242,617,500 Total Amendment No.1 inc VAT 1,447,517 24,668,792,500 Variance Against Original Contract + 3,07 + 4,72

3.2 DSC Consultants

A Design and Supervision Consultant DSC will be responsible for design of WP-2 and WP- 3 civil works and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II, and will be based in Padang, West Sumatera. DSC has been established in Balai II Padang following the contract signing on 11 June 2013 between Balai II and Renardet SA in joint venture with PT. Cipta Strada, PT. Daya Creasi Mitrayasa, PT. Seecons and PT. Yodya Karya. The Notice To Proceed was issued by the Balai II on 19 June 2013. Shown in Table 3.3 is the present status of the Design Supervision Consultant DSC contract. Table 3.3 Form of Currency USD IDR Original Contract 820,600 51,818,705,000 VAT 10 GOI Portion 82,060 5,181,870,500 Total 920,660 57,000,575,500

3.3 Technical Assistance for Capacity Building for Disaster Risks Reduction

Consultant still to be procured

3.4 Technical Assistance for Capacity Building for Environmental Management

Consultant still to be procured

3.5 Technical Assistance for Capacity Building for Road Safety

Consultant still to be procured Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 17 4 CIVIL WORKS

4.1 Detailed Design Preparation

Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed for all projects proposed for WP-1. WP-2 nine subprojects and WP-3 eight subprojects will be designed by DSC and the construction supervision of all the works programs will be performed by the DSC. In parallel with the instruction to speed up the process, detailed engineering design DED of some subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. The CTC has been instructed by DGH to review the DED of seven packages completed by the P2JNs package 5, 6, 11, 13, 15, 17 and 19. The CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer attended the meeting with the DSC team on 3th, 5th and 7th March 2014 in order to discuss finalize about the additional Technical Design Road Safety comment and recommendation which are 4 packages781012 of AWP-2, in West Sumatra province and handed over to the DSC team on 6th February 2014. Final Project Management Manual for RSA which is Chapter 10.11 Road Safety Audit in the WINRIP Project Management Manual has been prepared by senior road safety audit engineer from 1th March to 25th March 2014 in order to be intended as a guide for project management and implementation of the project in aspect of road safey audit. The final Project Management Manual which is Chapter 10.11 Road Safety Audit in the WINRIP Project Management Manual: WINRIP Loan IBRD No. 8043-ID has been submitted on 25th March 2014. In addition, the CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer attended the meeting with the PU staffs on 18th March and 19th March 2014 in order to discuss finalize about the Project Management Manual with the charging staffs in the PU each field in order to reflect the latest guideline, manual and methodology to implement the project. Final Design Technical Review of 1 package No.16 SEBLAT-IPUH Link No.009.4, Bengkuliu Province which is WINRIP AWP-3 in Bengkulu province has carried out by the CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer in order to assess and finalize the technical quality review to the design preparation which has prepared by DSC team, in response to recommendation of the links for betterment and their implementation under third year Annual Works Program AWP-3, and consists of Quality Assurance Road Safety Audit of Technical Assistance for National Highway, from 17th March 2014 to 27th March 2014. and then CTC team has prepared additional Technical Design Road Safety CAMcomment and recommendation for realistic improvement regarding DED in order to provide the last chance to the DSC team so as to change the design before actual construction of the road. The final recommendation which is to finalize technical quality assurance in aspect of highway and road safety for DED has been submitted