Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 45
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui – Biha
Social Issues:
The Larap report of Package no.04 Krui – Biha Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report had been submitted to the
World Bank by PMU dated 10 April 2013. The WorldBank has reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Contract signing for the Package no.01Krui – Biha dated 25 Nov 2013.
Environmental Issues:
CTC need to carried out training of RKPPL to DSC and contractor staff cause of no
environmental specialist in DSC Team.
CTC has been check the recommendation of AMDAL to field and under coordination with DSCcontractor to input the environmental issues on the design.
6.6.2 Package No.02: Padang Sawah – SimpangEmpat
Social Issues:
The Larap report of Package No.02Padang Sawah – SimpangEmpatWest Sumatera Province has already approved by the World Bank dated 13 January 2013, and the
monitoring report has been submitted to the World Bank by PMU dated 2 April 2013. The WorldBank has reviewed the report dated 18 April 2013 required revision to be provided by
DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 5 July 2013. A monitoring report has been submitted to the World Bank by
PMU dated 15 July 2103, and approval from the World Bank dated 19 July 2013. The
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 46
project Sumaterathe remaining of 21 affected people did not receive compensation from Local Government yet. Now CTC is waiting a proof of the compensation payment for 21
affected people from local government. Contract signing for the Package no.02Padang Sawah - Sp.Empat dated 6 Dec 2013.
Environmental Issues: CTC need to carried out training of RKPPL to DSC and contractor staff cause of no
environmental specialist in DSC Team. CTC need check the recommendation UKLUPL bridge to field for clearance of
environmental issues wich integrate in to the design.
6.6.3 Package No.03: Manggopoh – Padang Sawah
Social Issues:
The Larap report of Package no.03 Manggopoh - Padang SawahWest Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report
has been submitted to the World Bank by PMU dated 2 April 2013. The WorldBankhas reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people did not receive compensation from Local
Government yet. CTC has received proof of the compensation payment for 5 from 15 affected people from local government. A monitoring report has submitted to the World
Bank dated 28 February 2014.
Contract signing for the Package no.03Manggopoh – Padang Sawah dated 6 Dec 2013.
Environmental Issues: CTC need to carried out training of RKPPL to DSC and contractor staff cause of no
environmental specialist in DSC Team.
6.6.4 Package No.04: Ipuh – Bantal
Social Issues:
The Larap report of Package no.04 Ipuh – Bantal has already approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of
227 PAPs from Head of Satker PJN II Bengkulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank
dated 24 December 2013. Compensation payment for the remaining 70 from 227 PAP has paid by the World Bank, and a monitoring report has submitted to the World Bank dated 28
February 2014. Contract signing for the Package No.04 Ipuh – Bantal dated 14 Nov 2013.
Environmental Issues: