Monitoring Report of the LARAP for Ipuh – Bantal
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 25
a. All five Larap reports that there are some assets land and building that will be affected entirely. Following the LARPF WINRIP should be covered on land acquisition and
resettlement and need to budget.
b. On the Larap report for package for Ipuh – Seblat there are 126 land plots belong to governmentpublic that are affected. However the social economic survey and the
inventory table do not show the situation.
According to the World Bank letter, PMU via Ref. 1476Bp.11MD2013 dated 27 November 2013 Director of Planning has requested the Director of Implementation Affairs Region I via
the SatkerPPK to prepare the addresed above.
A revision for five Larap reports had been submitted to the World Bank on 9 January 2014, and PMU had been received some comments from WB 16 January 2014. All of the Bank’s
request will be provided by PMU on the Larap monitoring report. Final revision for five Larap reports including the signed action plan is under submission process to the World Bank.
Now, PMUCTCis waiting Larap implementation report from Head of Satker I and II Bengkulu Province.