Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 33
c.
Document Library System, used to record all information of hard copy documents then store it into library shelves.
Following further review the sub folder server file system has been amended to accommodate the needs of the professional staff as follows:
CODE ROOT
1
st
FOLDER 2
nd
FOLDER
01 01_Project_Document
01_01 01_01_PIP
01_02 01_02_Loan_Agreement
01_03 01_03_Loan_Agreement_Extention
01_04 01_04_PAD
01_05 01_05_PMM
01_06 10_06_Aide_Memoire
02 02_General_Contract
02_01 02_01_Pre-contract
02_02 02_02_Contract
02_03 02_03_Mobilization
02_04 02_04_Amendment
02_05 02_05_Addendum
02_06 02_06_MOA
03 03_General_Report
03_01 03_01_Inception_Report
03_02 03_02_Monthly_Progress_Report
03_03 03_03_IFR
03_04 03_04_IFR_Q
03_05 03_05_Procurement_Committee_Readin
ess_ Assessment_Report
03_06 03_06_Bid_Evaluation_Procurement_Rep
ort 03_07
03_07_Draft_Project_Completion_Report 03_08
03_08_Project_Completion_Report 03_09
03_09_Technical_Report 04_01
04_General_Letter
05
05_General_Document ation
05_01 05_01_Meeting
05_02 05_02_Workshop
05_03 05_03_Training
05_04 05_04_Site_Visit
06 06_Office_Manager
06_01 06_01_Document
06_02 06_02_Operational
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 34
CODE ROOT
1
st
FOLDER 2
nd
FOLDER
07 07_Highway
07_01 07_01_General
07_02 07_02_Design_Review
07_02_01 Package 1,
2, 3, 4 07_03
07_03_Auditor 07_03_01
Package 1, 2, 3, 4
07_04 07_04_Meeting
07_05 07_05_Report
08 08_Quality_Assurance
08_01 08_01_General
08_02 08_02_Meeting
08_03 08_03_Report
09 09_Financial
09_01 09_01_General
09_02 09_01_Meeting
09_03 09_01_Report
10 10_Environmental
10_01 10_01_General
10_02 10_02_Environmental_Review
10_03 10_03_Environmental_Studies
10_04 10_04_HIVAIDS
10_05 10_05_Monitoring
10_06 10_06_Meeting
10_07 10_07_Report
11
11_Social_Impact
11_01 11_01_General
11_02 11_02_LARAP_Review
11_03 11_03_Monitoring
11_04 11_04_Meeting
11_05 11_05_Report
12 12_Procurement
12_01 12_01_General_Procurement_Notice
12_02 12_02_Special_Procurement_Notice
12_03 12_03_Bidding
12_03_01 CTC
12_03_02 DSC
12_03_03 Civil Works
12_03_04 Capacity
Building 12_03_05
Disaster
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 35
CODE ROOT
1
st
FOLDER 2
nd
FOLDER
Management 12_04
12_04_Meeting 12_05
12_05_Report 13
13_Data_and_Informat ion
13_01 13_01_General
13_02 13_02_Source_Code
13_03 13_03_Master_Software
13_04 13_04_Meeting
13_05 13_05_Report
14
14_Community_Devel opment
14_01 14_01_General
14_02 14_02_ACAP_Review
14_03 14_03_WPM
14_04 14_04_PP3
14_05 14_05_Meeting
14_06 14_06_Report
15 15_Supporting_Staff
15_01 15_01_Tedi_Okta_Pratama
15_02 15_02_Banu_Amanda_Zuhri
15_03 15_03_Data_Manager
15_04 15_04_Bayu_Rendro
Each folder will only be able to be accessed by responsible and nominated staff members to prevent any undesirable alteration or addition to the stored material.
Each engineer will save every document into its correct folder which will be backed up weekly by the Database Specialist on a 2 TB of external hard disk.
5.3.3. Financial Management Information System FMIS
The application of Financial Management Information System FMIS is built to stored the data of project progress every month. The project progress and financial
information is retrieved from the MC Monthly Certificate that made by the contractor or consultant at submission of invoice. And we expected to know the progress status
of each package will always be updated every month. In the next 2 months we are developing the FMIS application. You can see the progress with the URL address
http:fmis.winrip-ibrd.com .
5.3.4. Website
The official website of the WINRIP is already completed and online in August 2013. And is currently being carried update articles and documents related to the WINRIP
project. Please check the URL address: http:www.winrip-ibrd.com
.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 36
HOME ABOUT
NEWS DOCUMENT
REPORT PROCUREMENT
ACAP GALLERY
APPLICATION FOOTER
WINRIP PMU
CTC DSC
Document Report
Project Highway
Social and Environment
Community Development
Procurement Progress Report
Financial Report Audit Report
Annual Report Progress
Report Financial
Report Audit
Report Annual
Report Procurement
Plan Bidding
Information Procurement
Contract Goods
Consultant Civil Works
CHS Pengaduan
CRO WPM
TPM PP3
Public Information
Photo Video
Presenta- tion
File Storage WebGIS
CHS PMS
Procedure Complaint Form
Complaint Report
Document Selection
Data Report
Document Selection
Data Report
Contact Copyright
Site Map of WINRIP website. The WINRIP website contains all of the following items:
a General WINRIP information including copies of all reports i.e. Monthly Progress Reports and Quarterly Progress Reports, Social and Environmental Status
Reports and the Road Safety Audit Reports. b Project list and Project Progress Status including Procurement Plan and Bid Winners,
and Copies of all Bid Documents. c ACAP and Complaint Handling System including contact points, list of Community
Representation Observers, and list of Third Party Monitors. d Documents, including all reports and bidding documents.
e Gallery and other important information. f Package Location Map.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 37
6 PROJECT PERFORMANCE
6.1 World Bank and GOI Compliance
6.1.1 World Bank Missions
A World Bank mission took place between April 28 and onward to May 13, 2014 to review the implementation status of the Western Indonesia National Roads Improvement Project
WINRIP. The mission was comprised of Elisabeth Goller Task Team LeaderSr. Transport Specialist, Amilia Aldian Transport Engineer, Budi Permana Procurement Specialist,
Agus Sjamsudin Road Engineer, María José Sala Pelufo Transport Specialist, Novira Kusdarti Asra Sr. Financial Management Specialist, Achmad Affandi Nasution
Governance and Anti-Corruption Specialist, Dennie Stenly Mamonto Environmental Specialist, Francisca Melia Setiawati Social, Land AcquisitionResettlement Specialist, and
Yulita Sari Soepardjo Team Assistant. The Bank team held kick-off meetings with the Project Implementation Unit PMU in the
Directorate General of Highways DGH and the project consultants on April 28, 2014. A number of meetings are scheduled to be held during the last week of April and in the first
week of May. The Bank team are going to visit several project locations in West Sumatra from May 6 to May 9, 2014. The final wrap-up meeting with Bappenas is schedule during
the middle part of May 2014. These will be recorded in the next MPR.
6.1.2 Performance Indicators
GOI and the World Bank have agreed on a set of Key Performance Indicators KPIs to measure the project’s performance in achieving its stated development objectives. These
KPIs are provided in the World Bank’s Project Appraisal Document PAD, together with baseline data and targets.
The annual targets for KPIs that are indicated in the Project Appraisal Document are based on the initial Project Implementation Schedule as shown in Appendix I.
The CTC is concentrating on the establishment of precise definitions, calculation methods and data collection procedures to monitor the KPIs.
6.2 Implementation Support Components
6.2.1 Core Team Consultant CTC
The CTC is responsible to provide support to the PMU and DGH in the management of the Project, based in Jakarta. The CTC tasks include financial and progress monitoring and
reporting, information management and dissemination, quality assurance and performance review for the Design and Supervision Consultants DSC, implementation and monitoring of
the anti-corruption action plan, support for project monitoring and evaluation, and support for implementation of a training program to support project management and implementation.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 38
The CTC contract No. 06-20CTCTALN80431112 was signed on 5 November 2012 by both DGH and a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and
PT. Epadascon Permata Engineering Consultant.
The main CTC activities during April 2014 included: •
Continue assistance to PMU as and when required. •
Prepare and submit Monthly Progress Report for April 2014 •
Prepare for Amandment No. 2. •
World Bank Meeting for Replacement Road •
Finalization PQ for Package No. 11 and 13 in Bengkulu •
Socialization for TPM in Bengkulu •
Third Party Monitoring Review in Lampung •
Monitoring LARAP Package No. 17 Sp. Gunung Kemala – Pg Tampak in Lampung •
Workshop for Updating PMM •
Meeting with Pokja Bengkulu Package No. 11 and 13 •
Meeting with World Bank WINRIP Coordination
6.2.2 Design and Supervision Consultant DSC
The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of ‘Engineer’ under
a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works,
environmental and social monitoring and management, and support for financial and progress monitoring and reporting.
The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as
documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the
effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II, and will be based in Padang, West
Sumatera.
DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March 2013 for
review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.
6.2.3 Road Sector Institutional Development
This component consists of technical assistance for capacity building for the new environmentrisk mitigation and road safety unit to enhance its capacity for disaster risk
assessment and planning, risk mapping of land-slides, coastal erosion, earthquake and floods, analysis of alternative road designs for road segments passing through critical
environmental assets and vulnerable areas.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 39
It is planned so far that there will be three 3 consultant services for: •
Capacity Building of Disaster Risks Reduction •
Capacity Building for Environmental Management •
Capacity Building for Road Safety Draft of the respective Terms of Reference has been being finalized by the Sub-Directorate
of Environment and Road Safety outlining the proposed scope activities for the component.
During preparation of this Report, the procurement for consultants under this component has not yet been started. Preparation for the procurement would be coordinated by the
PMU, the DGH Procurement Team and the CTC.
6.3 Training
6.3.1 Training and Workshop on Anti Corruption and Environmental Mitigations :
There was no training, workshop or seminar conducted by CTC during this month. However , the CTC’s Training Specialist in coordination with Community Development Officer and the
Environmental Specialist prepared all the material handouts for the proposed schedule trainingworkshop by the end of next month.
6.3.2 Annual Training Program
Examining some existing documents and information from previous projects SRRP, DGRI TrainingEIRTP-1, EIRTP-2: TOR, training report, training modules, etc.
Inquiring and asking for clarification concerning various aspects related to training delivery, e.g.: course programs, standard procedures and mechanism of training
operation within the CTC WINRIP, target groups and their requirements, etc.
Proposing for adding the position of a sub-professional staff, i.e. Assistant Training Specialist or Training Technician to be included in the Amendment No. 2.
Preparing Summary of Training Program tentative and Training Course Synopsis.
Consulting with relevant Specialists concerning the Course Synopsis to define the important points of contents meeting the project needs and therefore should be included.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 40
6.4 Anti‐Corruption Issues
6.4.1 Anti-Corruption Action Plan ACAP
The main duties of the Community Development Officer are implemented of Anti-Corruption Measures, and Monitoring their Effectiveness. Provide assistance as required with the
establishment of anti-corruption measures necessary to support the project, and monitor and report their effectiveness based on the Anti-Corruption Action Plan ACAP agreed between
the World Bank and the DGH.
The following tasks particularly need to establish procedures to be undertaken:
Selection of Community Representative Observers CROs of civil society groups to attend the procurements process on key procurement steps including pre-bid meeting
and site visit, bids submission and bids opening, and the announcement of the bid winner. These CROs will be invited from local universities or other selected independent
institutions, and will sign the attendance list for the procurementselection process.
Establishment of a Third Party Monitoring TPM mechanism, whereby the media and
civil society groups can become involved in monitoring the progress of the project. This mechanism will include regular sharing of information with the media.
Establishment and Management of a Complaints Handling Mechanism CHM, which
includes maintaining project complaint log and filing to monitor status of follow-up of each complaint. This mechanism will include provision for follow up investigations of
substantial complaints by the Inspectorate General of Ministry of Public Works or third party audit to ensure independence and reliability of the system. The CTC assignment
concerns the monitoring of the aspects of Anti-Corruption Action Plan ACAP implementation and where required act pro-active in resolving issues when such a
matter arises. The Community Development specialist has a major role in monitoring performance and assists PMU in the set-up and follow-through of the Complaints
Handling Unit CHU for the ACAP related incidents
Enhanced Disclosure Provisions and Transparency, Ministry of Public Work MPW will
provide necessary information in the Project Implementation Plan PIP, Project Management manual PMM on their website, and in the bidding documents, such as
contact point for complaint mail and e-mail address, phone, fax, text message. The contact will also include the Bank’s Fraud and Corruption Hotline. MPW will hold Annual
Accountability Meetings to enhance accountability and project information sharing with civil society. The PMM will provide guidelines on disclosure of information related to the
project. MPW official website will display critical information on WINRIP to enhance both internal and external monitoring of the project
6.4.2 Community Representative Observers CRO
The Anti-Corruption Action Plan ACAP activities on Community Representative Observers CROs during September 2013, was adjusted and supported the progress of procurement
activities.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 41
During April 2014 was no activity on the Community Representative Observers CROs, because CROs for four AWP-1 packages package 01, 02, 03, and 04 has finished at the
Announcement of Bid Winners of in November 2013. The Annual Work Program-2 AWP-2 is not yet ready for tender, so there is no procurement activities, therefore the CRO activity
was not be held.
The activities progress of Community Representative Observers CROs from January 2013 until April 2014, as shown in Appendix H1.
6.4.3 Third Party Monitoring TPM
Interview of TPM candidates for the four AWP-1 packages and evaluation of their proposal has been done during March 2014. In April had been planned for some follow-up of TPM
activities such as: ‘
Delivery of preparatory training for selected TPM teams; Assist the Officer in Charge of PMU to prepare the Approval letter of the TPM teams;
Provision Decree of the Director of Planning of DGH concerning the formation of Third
Party Monitoring for four packages of AWP-1 WINRIP; Providing the Letter of Employment Agreement Memorandum of Understanding
between the TPM teams with CTC WINRIP on behalf of PMU WINRIP. The delivery of preparatory training for selected TPM teams activity could not be done in
April 2014, due to the lack of certainty of the availability funding for the ACAP activities on CTC WINRIP original contract, therefore the TPM activity in April focused on the preparation
of the Technical Justification for propose of additional funds for anti-Corruption Action Plan on Amendment 2 of the CTC contract.
The Approval letter of the TPM teams by the Officer in Charge of PMU has been prepared, and will be signed when preparatory training has been carried out.
Likewise, the establishment of the Decree of the Director of Planning, DGH concerning the formation of TPM teams for four packages of AWP-1 WINRIP, and providing the Letter of
Employment Agreement Memorandum of Understanding between the TPM teams with CTC WINRIP on behalf of PMU WINRIP have been drafted.
The Progress of Third Party Monitoring TPM Activities from April 2013 up to March 2014 and the works plan is shown in Appendix H2.
6.4.4 Complaint Handling System CHS
The Community Development Officer with collaboration with MIS Specialist has developed a software application of Complaint Handling System CHS in integrated to website of
WINRIP http:www.winrip-ibrd.com.
In the implementation of Complaint Handling System CHS essentially there are four main components as follows:
•
Data Entry.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 42
•
Complaint Registration.
•
Complaint Assessment.
•
Field Clarification and Analysis.
•
Problem Solving and taking the Decision The final draft of Complaint Handling System the framework of the complaint procedures on
the web site of WINRIP and provided ACAP inputting data in the web site has been finished at the end of February 2014, and ready to be operated.
However these applications still continue to be refined by considering input from various parties. One of the efforts in order to improve the CHS application is to hold meetings with
the World Bank on 30 April 2014, to discuss and receive the input from them. This meeting was attended by Mr. Fandi Nasution GAC World Bank and Ms. Novira K. Asra FMS World
Bank, and CTC WINRIP teams Co-Team Leader, Community Development team, and MIS team.
Some conclusions from the meeting were:
•
The disclosure of information widely to public, so that they can easily provide feedback to the elements involved in project management.
•
It is expected that the public can easily give feedback, information, steam, grievance or complaints about the implementation of the project.
•
Complaints submitted outside the WINRIP system eg through articles or reader letters of the newspaper, the results of audits, complaints to the legislature DPR DPRD,
Ministry of Public Works regional Public Works agencies , other government agencies, need to be tracked to proactively.
•
Maximum extent as possible utilizing the resources websites that have been available on the Ministry Public Works such as http:www.pu.go.id, Integrated Project Monitoring
System Sistem Pemantauan Proyek Terpadu SiPP http:103.12.84.51sippterpadu, the Presidential Work Unit for Supervision and Control of Development Unit Kerja
Presiden
Bidang Pengawasan
dan Pengendalian
Pembangunan UKP4
http:www.ukp.go.id.
•
In order to improvement the CHS, need to be coordinated with relevant agencies or units within the MPW.
The CHS Activities is shown in Annex H3.
6.4.5. Publication Disclosures
Publication and disclosure is an attempt to increase transparency of information to the public, so the public can easily to access information about the project WINRIP. Some
components of publication and disclosures are as follows: a announcing the information about the project through newspapers, and dissemination of leaflets, b installation of the
project information boards, c the provision of space project information booth, d providing important information that can only be accessed by public with submitted an officially
applications to the authorities, and e the provision of information in the website which can
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 43
be accessed via the internet. Information provision dissemination about the Public Disclosures and Transparencies will
be done in lines on the preparatory training of TPM and other regularly training likes : Project Management Manual PMM, Procurement training, Interim Financial Report IFR
and other relevant trainings. Another way is to inputting the informationdata or to upload the articles into the website of WINRIP.
The public disclosures and transparencies information activities shall be started on the preparatory training on TPM in the near future
.
The Works Plan Activities for Publication Disclosure is shown in Annex H4.
6.4.6. Problem and Solutions
The problem is there is not available of the financing post in CTC WINRIP contract for implementation the Anti-Corruption Action Plan ACAP components, so there is uncertainty
on the future activities of ACAP.
The solution is to propose the additional financing on the implementation of the Anti- Corruption Action Plan ACAP components in Amendment 2 of CTC Contract. For
submission of this proposal has been prepared technical justification.
6.4.7. Action Plan for Next Months
The Activities plan for future months May – June of 2014, in order of priority are as follows: 1. In order to improvement the CHS, need to be coordinated with Sub Directorate of
Information and Communication, Directorate of Planning DGH on the subject Integrated Project Monitoring System Sistem Pemantauan Proyek Terpadu SiPP, including
completion process of suggestions and complaints from the public.
2. Carrying out the preparatory training to the elected TPM, which will be followed also by the related project implementer components PIU, PPK, Supervision Consultant DSC,
and Contractor. 3. Provision Decree of the Director of Planning, Directorate General of Highways
concerning Establishment of Third Party Monitoring for four packages of AWP-1 WINRIP. 4. Preparing Letter of Employment Agreement between the TPM of four packages of AWP-
1 with CTC WINRIP on behalf of PMU WINRIP.
5.
Inputting or upload the data
, documents
and reports of CROs and TPM into
the
website.
6.
Disseminate of Anti-Corruption Action Plan to all stakeholders who associated with the WINRIP project through the PMM training
.
7. Conducting socialization of CRO selection for the packets that will immediately be conducted the procurement of construction services, especially for Procurement
Committee of North Sumatra province Balai BPJN I Medan, for package 17: Simpang Rampa - Poriaha and package 15: Sibolga – Batas Tapanuli selatan.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 44
Note: For activities point 1, 2 and 3 are dependent upon the amendment 2 of CTC contract,
related to the availability of funds for the implementation of ACAP components, especially for the delivery of CRO and TPM.
The activities point 6 is depend to the readiness of the procurement team, if the procurement of the package is ready, it will be held the CRO.
6.5 Road Safety Audit
6.5.1 No activity done during this month
6.5.2 Current status of the project for technical field as of 31 April 2014.
The Details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of April 2014 is included as Appendix B.
Technical Design Review Road Safety Audit Report Status Group
Pack No.
Name of Sub-project Technical Design Review Road Safety Audit
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
AWP -2
5 Sp.Rampa – Poriaha
Link No.015.xx completed completed completed
completed Final Technical Report is
resubmitted on 17th September 2013
6 PS.Pedati - Kerkap
Link No.010.0 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
7 Indrapura – Tapan
Link No.019.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 5th February 2013
8 Bts.Pariaman – Manggopoh
Link No.024.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 5th February 2014
9 Rantau Tijang – Kota Agung
Link No.026.1 10
Sp.Empat – Sp. Air Balam Link No.034.1
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 5th February 2014 11
Bantal - Mukomuko Link No.015.2
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013 12
Kambang – Indrapura Link No.017.2
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 5th February 2014 13
SP.Rukis - TJ.Kemuning Link No.006.0
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed completed
Final Technical Report is submitted
on 23th September 2013
16 Seblat – Ipuh
Link No.010.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th March 2014
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 45
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui – Biha
Social Issues:
The Larap report of Package no.04 Krui – Biha Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report had been submitted to the
World Bank by PMU dated 10 April 2013. The WorldBank has reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Contract signing for the Package no.01Krui – Biha dated 25 Nov 2013.
Environmental Issues:
CTC need to carried out training of RKPPL to DSC and contractor staff cause of no
environmental specialist in DSC Team.
CTC has been check the recommendation of AMDAL to field and under coordination with DSCcontractor to input the environmental issues on the design.
6.6.2 Package No.02: Padang Sawah – SimpangEmpat
Social Issues:
The Larap report of Package No.02Padang Sawah – SimpangEmpatWest Sumatera Province has already approved by the World Bank dated 13 January 2013, and the
monitoring report has been submitted to the World Bank by PMU dated 2 April 2013. The WorldBank has reviewed the report dated 18 April 2013 required revision to be provided by
DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 5 July 2013. A monitoring report has been submitted to the World Bank by
PMU dated 15 July 2103, and approval from the World Bank dated 19 July 2013. The
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 46
project Sumaterathe remaining of 21 affected people did not receive compensation from Local Government yet. Now CTC is waiting a proof of the compensation payment for 21
affected people from local government. Contract signing for the Package no.02Padang Sawah - Sp.Empat dated 6 Dec 2013.
Environmental Issues: CTC need to carried out training of RKPPL to DSC and contractor staff cause of no
environmental specialist in DSC Team. CTC need check the recommendation UKLUPL bridge to field for clearance of
environmental issues wich integrate in to the design.
6.6.3 Package No.03: Manggopoh – Padang Sawah
Social Issues:
The Larap report of Package no.03 Manggopoh - Padang SawahWest Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report
has been submitted to the World Bank by PMU dated 2 April 2013. The WorldBankhas reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people did not receive compensation from Local
Government yet. CTC has received proof of the compensation payment for 5 from 15 affected people from local government. A monitoring report has submitted to the World
Bank dated 28 February 2014.
Contract signing for the Package no.03Manggopoh – Padang Sawah dated 6 Dec 2013.
Environmental Issues: CTC need to carried out training of RKPPL to DSC and contractor staff cause of no
environmental specialist in DSC Team.
6.6.4 Package No.04: Ipuh – Bantal
Social Issues:
The Larap report of Package no.04 Ipuh – Bantal has already approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of
227 PAPs from Head of Satker PJN II Bengkulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank
dated 24 December 2013. Compensation payment for the remaining 70 from 227 PAP has paid by the World Bank, and a monitoring report has submitted to the World Bank dated 28
February 2014. Contract signing for the Package No.04 Ipuh – Bantal dated 14 Nov 2013.
Environmental Issues:
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 47
Regarding to the implementation of the Review Mission on December 9 to 11 December 2013 in Province of Bengkulu and comments from the World Bank Environmental Expert
related to the safeguards environmental documents for Package no.4 Ipuh Bantal, then based on observations in the field and the regulationsrequired environmental safeguards
more then SPPL.Therefor the PMU has requested technical considerations from the Head of Subdirectorate of Environmental and Road Safety by the formal letter dated 16 Dec 2013.
CTC need to carried out training of RKPPL to DSC and contractor staff cause of no environmental specialist in DSC Team.
CTC will asist the consultant to decided of sampling point and environmental mitigation of project.
6.6.5 Package No.05: Sp. Rampa – Poriaha
Social Issues:
The Larap report of Package no.05Sp.Rampa – Poriaha North Sumatera Province has already submitted to the World Bank by PMU dated 30 August 2013. The WorldBank has
reviewed the report dated 16 September 2013 and required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a Larap report, and submited to the PMU dated 29October 2013. Larap report has been submitted to the World Bank by
PMU dated 6 November 2103, and approval from the World Bank dated 12 November 2013 that documents disclosed at PMU website.
Referring to the letter from World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding to the
approval of the report from the World Bank to be informed to Balai I North Sumatera Province. Now, PMUCTC is waiting report of implementation of the Larap from Head of
Satker PJN II North Sumatera Province.
Environmental Issues:
CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design.
6.6.6 Package No.06: Psr.Pedati – Kerkap
Social Issues:
CTC received a Larap report of Package no.06Psr.Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report
during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2013 and approval the
World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revised by CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 48
negotiation.The final revision of Larap including signed action under submission process to the World Bank by PMU.
Environmental Issues: CTC need check the recommendation of UKLUPL to field for clearance of
environmental issues wich integrate in to the design.
6.6.7 Package No.07: Indrapura – Tapan
Social Issues:
CTC received from Balai IIP2JN Padang Larap report of Package no.07Indrapura – Tapanduring on January 2014.Larap report already reviewed by CTC, and Directorate
Implementation Region I being send Memo to Balai II.
Environmental Issues: CTC need check the recommendation of AMDAL to field for clearance of environmental
issues wich integrate in to the design. CTC a waiting Amdal documents from the Subdit TLKJAMDAL consultant for submit to
the Bank.
6.6.8 Package No.08: Bts Kota Pariaman – Manggopoh
Social Issues:
CTC received the LARAP report from Balai II PadangPMU dated 01 August 2013. Review and comment from CTC has been sent to PMU dated 9 September 2013, and PMU has
forwarded to P2JNLocal Consultant and requested to revise the LARAP report based on CTC comment.
Environmental Issues:
CTC need check the recommendation of AMDAL to field for clearance of environmental issues wich integrate in to the design.
6.6.9 Package No.09: Rantau Tijang – Kota Agung
Social Issues:
Balai III will provide a Larap Document for Rantau Tijang – Kota Agung.
Environmental Issues:
CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design.
6.6.10 Package No.10: Sp. Empat – Air Balam Social Issues:
CTC received the LARAP report from Balai II PadangPMU on 01 August 2013. Review and
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 49
comment from CTC has been sent to PMU on 9 September 2013, and PMU forwarded to P2JNLocal Consultant and has requested to revise the LARAP report based on CTC
comment.
Environmental Issues:
CTC need check the recommendation of AMDAL to field for clearance of environmental issues wich integrate in to the design.
6.6.11 Package No.11: Bantal - Mukomuko Social Issues:
CTC received a Larap report of Package no.11 Bantal - Mukomuko from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report
during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2103 and approval the
World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revisedby CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World
Bank by PMU.
Environmental Issues: CTC need check the recommendation of AMDAL to field for clearance of environmental
issues wich integrate in to the design.
6.6.12 Package No12: Kambang – Indrapura Social Issues:
CTC received the LARAP report form Balai II PadangPMU on 01 August 2013. Review and comment from CTC has been sent to PMU on 9 September 2013, and PMU has
forwardedto P2JN Local Consultant and requested to revise the LARAP report based on CTC comment.
Environmental Issues: CTC need check the recommendation of AMDAL to field for clearance of environmental
issues wich integrate in to the design. CTC a waiting AMDAL Doc from the Subdit TLKJ AMDAL Consultant
6.6.13 Package No.13: Sp. Rukis – Tj. Kemuning Social Issues:
CTC received a Larap report of Package no.13 Sp.Rukis – Tj.Kemuning from Balai III
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 50
PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report
already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revisedby CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World
Bank from PMU.
Environmental Issues: CTC need check the recommendation of UKLUPL to field for clearance of
environmental issues wich integrate in to the design.
6.6.14 Package No.14: Painan – Kambang Social Issues:
CTC received from Balai IIP2JN Padang Larap report of Package no.14Painan – Kambangduring on January 2014. Larap report already reviewed by CTC, and Directorate
Implementation Region I is being send Memo to Balai II.
Environmental Issues: CTC need check the recommendation of AMDAL to field for clearance of environmental
issues wich integrate in to the design. CTC a waiting AMDAL Doc from the Subdit TLKJ AMDAL Consultant
6.6.15 Package No.15: Sibolga – Bts. Tapsel Social Issues:
CTC received Final LARAP report form BalaiPMU on 30 September 2013. The report already submitted to the Bank on 22 October 2013 and approved by the Bank on 28 October
2013 with some comments.
Follow up the WorldBank review and PMU letter, now the Larap report is being revisedby CTC. A revision Larap reports has been submitted to the WB dated 30 January 2014 and
approval from the WB dated 6 February 2014.
Environmental Issues: CTC need check the recommendation of UKLUPL to field for clearance of
environmental issues wich integrate in to the design.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 51
6.6.16 Package No.16: Sebelat – Ipuh Social Issues:
CTC received a Larap report of Package no.16 Sebelat - Ipuh from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report during November
2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2103 and approval the World Bank dated 20
November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revisedby CTC. A revision of the Larap report has been submitted to the World Bank dated 9 Jan 2014
and approval from the WB dated 16 Jan 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report,
and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World Bank from PMU.
Environmental Issues: CTC need check the recommendation of AMDAL to field for clearance of environmental
issues wich integrate in to the design.
6.6.17 Package No.17: SP. Gunung Kemala – Pg. Tampak Social Issues:
The Larapreporthas reviewed by CTC and submitted to PMU dated 30 August 2013. The report already submitted to the World Bank by PMU dated 10 September 2013 and approval
the World Bank dated 16 September 2013 with some comment
The revision of Larap Report submitted to PMU byCTC dated 29 October 2013. The report already submitted to the World Bank dated 06 November 2103 and responsed by the Bank
on 12 November 2013and that documents disclosed at PMU website.
Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report
from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTCis waiting a report of Larap implementation from Satker in Lampung
Province.
Environmental Issues: CTC need check the recommendation of AMDAL UKLUPL to field for clearance of
environmental issues wich integrate in to the design.
6.6.18 Package No.18: Mukomuko – Bts. Sumbar Social Issues:
Balai III will provide Larap Document for this package.
Environmental Issues: CTC need check the recommendation of AMDAL to field for clearance of environmental
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 52
issues wich integrate in to the design.
6.6.19 Package No.19: Lais - Bintunan Social Issues:
CTC received a Larap report of package no.19 Lais - Bintunan from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report
during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2103 and approval the
World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revisedby CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World
Bank from PMU.
Environmental Issues:- CTC need check the recommendation of UKLUPL to field for clearance of
environmental issues wich integrate in to the design.
6.6.20 Package No.20: Lubuk Alung – Sicincin Social Issues:
CTC received from Balai IIP2JN Padang Larap report of Package no.20Lubuk Alung – Sicincinduring January 2014. Larap report already reviewed by CTC, and Directorate
Implementation Region I is being send Memo to Balai II.
Environmental Issues:
CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design.
6.6.21 Package No.21: Lubuk Alung – Kuraitaji Social Issues:
CTC received from Balai IIP2JN Padang Larap report of package No.21Lubuk Alung – Kuraitajiduring January 2014. Larapreport already reviewed by CTC, and Directorate
Implementation Region I is being send Memo to Balai II.
Environmental Issues:-
CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 53
6.7 Management Information System
The WINRIP official website has been completed and already online since August 2013. But it is still poor content of articles, news, documents, reports and media gallery. This is
because the data and information is not collected properly. So the Administrator initiated to collecting the data and information from the PMU and CTC. After some data and information
has been collected, then the Administrator is start uploading the articles, news, documents, reports and media gallery into the WINRIP website. Please see current conditions of the
WINRIP website with URL address at
http:www.winrip-ibrd.com . And the following is
detailed explanation of the process of data collection, data compilations, and upload the data to the WINRIP website in January 2014.
6.7.1. Data Colletion The updating data is often constrained by the human factor. The consultants and the
assistants are undisciplined to upload files to the server. To overcome this, Administrator needs to collecting data manually by visiting each consultants and assistants door to door to
the PMU dan CTC office.
a. List of data to be searched Here is a list of data that needed to upload into the WINRIP website.
Section No.
Data Type
Source
About 1
WINRIP Article
PMM 2
PMU Article
PMM 3
CTC Article
PMM 4
DSC Article
PMM News
1 Site Visit
Article Photo CTC
2 Training and workshop
Article Photo CTC
Document 1
Project Document
CTC 2
Highway Document
CTC 3
Environment Social Document
CTC 4
Procurement Document
CTC 5
Community Development Document
CTC Report
1 Project Progress
Report CTC
2 Management Report
Report CTC
Procurement 1
Procurement Plan Report
PMU 2
Bidding Information Repot
PMU 3
Contract Report
PMU ACAP
1 Complaint
Form CTC
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 54
Section No.
Data Type
Source
2 Community
Representative Observer
Report CTC
3 Third Party Monitoring
Report CTC
4 Disclosure of information
Article CTC
Gallery 1
Photo Media
CTC 2
Video Media
CTC 3
Presentation Media
CTC
b. Data storage The administrator using USB flash disk to copied all of data and documents from the
computer of each consultants and assistants. Then the files has sorted and stored in the external hard disk with space 2 TB. Furthermore, all files has uploaded to the File Storage
server as a data storage and archive documents.
6.7.2. Data Compilation Compilation of data is the data selection process, tabulation and grouping the data according
to predetermined categories. Administrators often obtain data and documents that are not in accordance with the requirements, that need to do the selection and grouping the data
according to predetermined requirements.
a. Sorting of data Sorting is the process of arranging data into meaningful order so that you can analyze it
more effectively. Sorting worksheet data also makes it easier to analyze. In this case the data collected by the need of article category on WINRIP website. Then make a check list of
where the data is already completed or not collected.
No. Document Type
Description
1 Management Report
The documents that created by CTC WINRIP and arranged in a period of time, such as Preliminary,
Monthly, Quarterly and Final.
2 Technical Report
The documents that created by experts in the CTC WINRIP in accordance with their task and section.
3 Documents
The documents that related to the WINRIP project. The document prepared in accordance with the types
of documents and sort by each package of the WINRIP project.
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 55
b. Converting files To make easier the process of uploading the data and archiving of documents, all of
documents must be converted into PDF files. And for files that can not be converted to a PDF, then it is collected and converted into a ZIP file. So all of users can easily download all
of document files from the WINRIP website.
+ + + +
All compressed into one ZIP file Each files must be converted to PDF file
ZIP
c. File names composition
The file name must be set with structured and neat. And information of the file should be summarized in a file names. Then it is easier to search that files later.
WINRIP Ducument Title
Description Date
Extention
_ _ _
_ _ .
Section Document Title
Description Date
Extention
: WINRIP Project : Author PMU, CTC, DSC
: Expert section : Document title
: Additional description of file : Year+Month+Date
: File extention
Section
WINRIP
PMUCTCDSC
PMUCTCDSC
Example: Before
BAB I Pendahuluan Revisi Akhir pisan.pdf Modification
WINRIP_CTC
_ HIGHWAY
_ SCM
_ Chapter I
_ 2013
. pdf