No activity done during this month

Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 46 project Sumaterathe remaining of 21 affected people did not receive compensation from Local Government yet. Now CTC is waiting a proof of the compensation payment for 21 affected people from local government. Contract signing for the Package no.02Padang Sawah - Sp.Empat dated 6 Dec 2013. Environmental Issues:  CTC need to carried out training of RKPPL to DSC and contractor staff cause of no environmental specialist in DSC Team.  CTC need check the recommendation UKLUPL bridge to field for clearance of environmental issues wich integrate in to the design.

6.6.3 Package No.03: Manggopoh – Padang Sawah

Social Issues: The Larap report of Package no.03 Manggopoh - Padang SawahWest Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report has been submitted to the World Bank by PMU dated 2 April 2013. The WorldBankhas reviewed the report dated 18 April 2013 required revision to be provided by DGH. According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people did not receive compensation from Local Government yet. CTC has received proof of the compensation payment for 5 from 15 affected people from local government. A monitoring report has submitted to the World Bank dated 28 February 2014. Contract signing for the Package no.03Manggopoh – Padang Sawah dated 6 Dec 2013. Environmental Issues:  CTC need to carried out training of RKPPL to DSC and contractor staff cause of no environmental specialist in DSC Team.

6.6.4 Package No.04: Ipuh – Bantal

Social Issues: The Larap report of Package no.04 Ipuh – Bantal has already approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of 227 PAPs from Head of Satker PJN II Bengkulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank dated 24 December 2013. Compensation payment for the remaining 70 from 227 PAP has paid by the World Bank, and a monitoring report has submitted to the World Bank dated 28 February 2014. Contract signing for the Package No.04 Ipuh – Bantal dated 14 Nov 2013. Environmental Issues: