Package No.10: Sp. Empat – Air Balam Social Issues:

Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 50 PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revisedby CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January 2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World Bank from PMU. Environmental Issues:  CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design.

6.6.14 Package No.14: Painan – Kambang Social Issues:

CTC received from Balai IIP2JN Padang Larap report of Package no.14Painan – Kambangduring on January 2014. Larap report already reviewed by CTC, and Directorate Implementation Region I is being send Memo to Balai II. Environmental Issues:  CTC need check the recommendation of AMDAL to field for clearance of environmental issues wich integrate in to the design.  CTC a waiting AMDAL Doc from the Subdit TLKJ AMDAL Consultant

6.6.15 Package No.15: Sibolga – Bts. Tapsel Social Issues:

CTC received Final LARAP report form BalaiPMU on 30 September 2013. The report already submitted to the Bank on 22 October 2013 and approved by the Bank on 28 October 2013 with some comments. Follow up the WorldBank review and PMU letter, now the Larap report is being revisedby CTC. A revision Larap reports has been submitted to the WB dated 30 January 2014 and approval from the WB dated 6 February 2014. Environmental Issues:  CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design. Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 51

6.6.16 Package No.16: Sebelat – Ipuh Social Issues:

CTC received a Larap report of Package no.16 Sebelat - Ipuh from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revisedby CTC. A revision of the Larap report has been submitted to the World Bank dated 9 Jan 2014 and approval from the WB dated 16 Jan 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World Bank from PMU. Environmental Issues:  CTC need check the recommendation of AMDAL to field for clearance of environmental issues wich integrate in to the design.

6.6.17 Package No.17: SP. Gunung Kemala – Pg. Tampak Social Issues:

The Larapreporthas reviewed by CTC and submitted to PMU dated 30 August 2013. The report already submitted to the World Bank by PMU dated 10 September 2013 and approval the World Bank dated 16 September 2013 with some comment The revision of Larap Report submitted to PMU byCTC dated 29 October 2013. The report already submitted to the World Bank dated 06 November 2103 and responsed by the Bank on 12 November 2013and that documents disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTCis waiting a report of Larap implementation from Satker in Lampung Province. Environmental Issues:  CTC need check the recommendation of AMDAL UKLUPL to field for clearance of environmental issues wich integrate in to the design.

6.6.18 Package No.18: Mukomuko – Bts. Sumbar Social Issues:

Balai III will provide Larap Document for this package. Environmental Issues:  CTC need check the recommendation of AMDAL to field for clearance of environmental