Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 23
people is being resolved by local government. A monitoring report will be submitted to WB if ready.
4. Monitoring Report of the LARAP for Ipuh – Bantal
Larap report of the package for Ipuh – Bantal in Bengkulu Province was approved the World Bank dated 10 December 2012. Up to the end of December 2013 CTC already receive a
proof of compensation payment for 157 of the total 227 affected peoples. A monitoring report submitted to the World Bankfrom PMU dated 24 December 2013, and received some
comment to the report from the World Bank dated 6 January 2014.Compensation payment for the remaining of 70 PAP has been paid by Local Government, and a monitoring report
has been submitted to the World Bank from PMU dated 28 February 2014. Contract signing for the package of Ipuh – Bantal dated 14 November 2013.
5. Monitoring Report of the LARAP for Sp. GunungKemala – PugungTampak
Larap report of the package for Sp. GunungKemala – PugungTampak in Lampung Province has reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 and need
revision as follows:
a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the
SpGunungKemala – PugungTampak links. Likewise the established price standard for the building compensation should refer to the current data updated data.
b. Action plan table should include a formation of the land appraising team, b moving 83 units of electricity utilities.
c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanation some data with no name in the nominative list.
e. Action plan signed by the relevant local government as a commitment that the local government will provide proper budget for the action plan
f. Implementation monitoring report by using the form provided in the LARAP.
According to WorldBank letter, PMU Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare
the addressed above.
Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. GunungKemala – PugungTampak. A revision of the Larap report already submitted to the
WB from PMU dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.