Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 21
environmental analysis is not required. Standard operational procedures SOP are used to handle any minor problem which may arise.
Details of packages that require environmental and social safeguards are given in Appendix D.
The following table provides a summary of the work involved are 21 packages. Bengkulu Province was conducted by Environmental Specialist during 13 – 15 March 2013
to check the status of land to be acquired, to estimate of land area which is affected by the project and to identify the type of land asset affected by project to carry out interview with
PAPs, to get information related land acquisition process and to check the current status of the Appraisal Team readiness for payment of the land acquisition. The CTC found that the
land and asset of PAPs have not been paid by the project. Until the end of April 2014, the land acquisition process is still ongoing.
4.6.2 Environmental and Social Issues
This section outlines the activities of the Social Impact Specialist and the Environmental Specialist during April 2014.
4.6.2.1 Environmental Issues
CTC is preparing the modul for training of the RKPPLCPEMP Contractor Program for Environmental Management Plan and Environmental Impact Management And Mitigation
Measures for the construction. CTC assisted Subdit Environmental Affairs to make coordination and discuss to produce those modul.
1. Monitoring of Environmental Aspects During Construction
CTC will circulated monitoring form to DSC. This set of forms which consist of 7 pages focused on environmental and social impacts. These forms were intended to be used every
month by the DSC Environmental Specialist.
CTC’s environmental staffs actively advises DSC on environmental monitoring, but have not directly carried out monitoring, despite the CTC TOR requirement to “to implement the
Environmental and Social Analysis Management Plan for WINRIP”, which involves monitoring of environmental plans and studies.
After finalizing the Standard Environmental Clauses, CTC assisted Subdit Environmental Affairs to produce monitoring forms covering all aspects of the technical specifications, and
introduced them to participants of environmental training including P2JN, Project Manager, DSC, Contractors, Team Work Pokja etc. There are 69 pages of forms, covering all
aspects of construction.
2. Design Integration, Road Safety aspects and Monitoring of Environmental Studies