Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 47
Regarding to the implementation of the Review Mission on December 9 to 11 December 2013 in Province of Bengkulu and comments from the World Bank Environmental Expert
related to the safeguards environmental documents for Package no.4 Ipuh Bantal, then based on observations in the field and the regulationsrequired environmental safeguards
more then SPPL.Therefor the PMU has requested technical considerations from the Head of Subdirectorate of Environmental and Road Safety by the formal letter dated 16 Dec 2013.
CTC need to carried out training of RKPPL to DSC and contractor staff cause of no environmental specialist in DSC Team.
CTC will asist the consultant to decided of sampling point and environmental mitigation of project.
6.6.5 Package No.05: Sp. Rampa – Poriaha
Social Issues:
The Larap report of Package no.05Sp.Rampa – Poriaha North Sumatera Province has already submitted to the World Bank by PMU dated 30 August 2013. The WorldBank has
reviewed the report dated 16 September 2013 and required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a Larap report, and submited to the PMU dated 29October 2013. Larap report has been submitted to the World Bank by
PMU dated 6 November 2103, and approval from the World Bank dated 12 November 2013 that documents disclosed at PMU website.
Referring to the letter from World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding to the
approval of the report from the World Bank to be informed to Balai I North Sumatera Province. Now, PMUCTC is waiting report of implementation of the Larap from Head of
Satker PJN II North Sumatera Province.
Environmental Issues:
CTC need check the recommendation of UKLUPL to field for clearance of environmental issues wich integrate in to the design.
6.6.6 Package No.06: Psr.Pedati – Kerkap
Social Issues:
CTC received a Larap report of Package no.06Psr.Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report
during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2013 and approval the
World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revised by CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting