Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 24
Referring to letter from the World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of
the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. PPKSatker and Government of Pesisir Barat already started land acquisition
preparation process, as establishment of land acquisition committee. Now, PMUCTC is waiting a report of Larap implementation from Head of Satker in Lampung Province.
6. Report of LARAP for Sp. Rampa - Poriaha
Larap report for Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 and need revision as follows:
a. Moving and providing compensation for one person kiosk owner affected must including to the action plan.
b. Action plan signed by the relevan local government as a commitment that the local government will provide proper budget for the action plan
c. Implementation monitoring report by using the form provided in the LARAP. According to WorldBank letter, PMU Ref. 1286Bp.11MD2013 dated 23 September 2013
has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above.
Follow up the WorldBank review and PMU letter, CTC revised the Larap report for Sp. Rampa – Poriaha. A revision of the Larap report already submitted to the WB from PMU
dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.
Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of
the report from the World Bank to be informed to Balai I North Sumatera. Now, PMUCTC is waiting a report of Larap implementation from Head of Satker North Sumatera Province.
7. Report of Five Larap in Bengkulu
CTC recievedLarap Reports for five 5 packages in Bengkulu Province from the BBPJN III Palembang dated 30 September 2013. The five of Larapreports are Larap for Package No.
13: Sp. Rukis – TanjungKemuning, Larap for Package No. 6: PsrPedati – Kerkap, Larap for Package No. 11: Muko-muko – Bantal, Larap for Package No. 16: Seblat – Ipuh, Larap for
Package No. 16: Bintunan – Lais.
CTC reviewed the five 5Larap Reports, and already submitted to the WorldBank from PMU dated 13 November 2013. All of the five Larap reports in Bengkulu Province have
reviewedbythe World Bank via Ref.WINRIP144 dated 20November 2013 and need revision as follows:
Monthly Progress Report April 2014
Western I ndonesia National Roads I mprovement Project 25
a. All five Larap reports that there are some assets land and building that will be affected entirely. Following the LARPF WINRIP should be covered on land acquisition and
resettlement and need to budget.
b. On the Larap report for package for Ipuh – Seblat there are 126 land plots belong to governmentpublic that are affected. However the social economic survey and the
inventory table do not show the situation.
According to the World Bank letter, PMU via Ref. 1476Bp.11MD2013 dated 27 November 2013 Director of Planning has requested the Director of Implementation Affairs Region I via
the SatkerPPK to prepare the addresed above.
A revision for five Larap reports had been submitted to the World Bank on 9 January 2014, and PMU had been received some comments from WB 16 January 2014. All of the Bank’s
request will be provided by PMU on the Larap monitoring report. Final revision for five Larap reports including the signed action plan is under submission process to the World Bank.
Now, PMUCTCis waiting Larap implementation report from Head of Satker I and II Bengkulu Province.
8. Report of LARAP for Sibolga – BtsTapsel
CTC received Draft Final Larap report for Sibolga – BtsTapsel from Balai dated 30 September 2013. The Larap report already submitted to the world Bank from PMU dated 22
October 2013, and approval the world bank dated 28 October 2013.
Larap report for Sibolga – BtsTapselin North Sumatera Province has reviewed by the World Bank Ref.WINRIP140 dated 28 October 2013 and need revision as follows:
a. There are some renters will be affected by the project which is also categorized as project affected people so must be recorded in the affected people list.
b. There is a private grave will be affected by the project which eligible to get moving cost and ritual ceremony cost.
c. There are 64 units of kiosks occupied side drain need to be displaced which get moving assistance in addition the compensation provided for their affected assets.
According to the WorldBank letter, PMU Ref. 1404Bp.11MD2013 dated 31October 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare
the addressed above.
A revision Larap reports had been submitted to the WBdated 30January 2014, and approval from the World Bank dated 6 February 2014. PPKSatker and Governor of North Sumatera
already started the land acquisition preparation stage process, like stage of determination of the location of the project, and coordination with local land agency. Now, PMUCTC is
waiting Larap implementation report from Head of Satker North Sumatra Province.