Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 19 The WINRIP updated Procurement Plan is attached as Appendix E.

4.3 Civil Works Implementation

All 4 contract packages under AWP-1 are currently under construction by different contractors. Commencement of works for all the 4 packages commenced on the 2 nd week of January 2014. Table 4.1 shows the background for each contract packages. Table 4.1 Program Contract Package Contractor Name of Road Province Contract Signed Notice to Proceed Contract Time AWP-1 1 Jaya Konstruksi Manggala Pertama Tbk Biha - Krui Lampung Nov 25, 2013 Jan 8, 2014 640 CD 2 Jaya Konstruksi Manggala Pertama Tbk Padang Sawah – Sp. Empat including Air Gadang West Sumatera Dec 6, 2013 Jan 6, 2014 730 CD 3 Jaya Konstruksi Manggala Pertama Tbk Manggopoh – Padang Sawah West Sumatera Dec 6, 2013 Jan 6, 2014 730 CD 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal Bengkulu Nov 14, 2013 Jan 10, 2014 730 CD

4.4 Civil Works Progress

As of the end of this reporting month, all the 4 contractors are still in the process of mobilization. Other activities done during this month were setting up of laboratory testing building, staking out and repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, construction of stone masonry side ditches and other minor works. Progress status of the four 4 on-going civil work contract as of this reporting period are shown in Table 4.2. For contract packages under AWP-2 and AWP-3 which have a combined total of 17 packages, a brief summary of the actual activities and status as of this reporting period are presented in Table 1.1, page 5 of this report. Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 20 Table 4.2 Program Contract Package Contractor Name of Road Target Progress Schedule Ending April 2014 Actual Progress Accomplis hed Slippage AWP-1 1 Jaya Konstruksi Manggala Pertama Tbk Biha - Krui 5,62 1,59 -4,30 2 Jaya Konstruksi Manggala Pertama Tbk Padang Sawah – Sp. Empat including Air Gadang 3,95 1,87 -2,08 3 Jaya Konstruksi Manggala Pertama Tbk Manggopo h – Padang Sawah 2,15 2,37 +0,22 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal 1,14 0,53 -0,61 As the Contractors were still in the mobilization stage, most of the delay incurred were attributed to difficulty in locating suitable base camps and quarry sites of unlimited quantities.

4.5 Quality Assurance

The DSC will be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. 4.6 Environmental and Social Considerations 4.6.1 Current Overall Situation A project category is assigned to each package as either Category A, B or C depending on the likely degree of influence on environmental issues with a brief explanation as follows. Category A project is one which will have a significant negative impact on the environment and may have an influence on areas outside the actual project area. A project classified as such requires an AMDAL ANDAL, RKLRPL study. Category B project is one which affects the people or the environment to some extent but with a smaller impact than a Category A. The required environmental analysis is a UKLUPL study only. Category C project has minimal effect on the people or environment and an