Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 43 be accessed via the internet. Information provision dissemination about the Public Disclosures and Transparencies will be done in lines on the preparatory training of TPM and other regularly training likes : Project Management Manual PMM, Procurement training, Interim Financial Report IFR and other relevant trainings. Another way is to inputting the informationdata or to upload the articles into the website of WINRIP. The public disclosures and transparencies information activities shall be started on the preparatory training on TPM in the near future . The Works Plan Activities for Publication Disclosure is shown in Annex H4.

6.4.6. Problem and Solutions

The problem is there is not available of the financing post in CTC WINRIP contract for implementation the Anti-Corruption Action Plan ACAP components, so there is uncertainty on the future activities of ACAP. The solution is to propose the additional financing on the implementation of the Anti- Corruption Action Plan ACAP components in Amendment 2 of CTC Contract. For submission of this proposal has been prepared technical justification.

6.4.7. Action Plan for Next Months

The Activities plan for future months May – June of 2014, in order of priority are as follows: 1. In order to improvement the CHS, need to be coordinated with Sub Directorate of Information and Communication, Directorate of Planning DGH on the subject Integrated Project Monitoring System Sistem Pemantauan Proyek Terpadu SiPP, including completion process of suggestions and complaints from the public. 2. Carrying out the preparatory training to the elected TPM, which will be followed also by the related project implementer components PIU, PPK, Supervision Consultant DSC, and Contractor. 3. Provision Decree of the Director of Planning, Directorate General of Highways concerning Establishment of Third Party Monitoring for four packages of AWP-1 WINRIP. 4. Preparing Letter of Employment Agreement between the TPM of four packages of AWP- 1 with CTC WINRIP on behalf of PMU WINRIP. 5. Inputting or upload the data , documents and reports of CROs and TPM into the website. 6. Disseminate of Anti-Corruption Action Plan to all stakeholders who associated with the WINRIP project through the PMM training . 7. Conducting socialization of CRO selection for the packets that will immediately be conducted the procurement of construction services, especially for Procurement Committee of North Sumatra province Balai BPJN I Medan, for package 17: Simpang Rampa - Poriaha and package 15: Sibolga – Batas Tapanuli selatan. Monthly Progress Report April 2014 Western I ndonesia National Roads I mprovement Project 44 Note: For activities point 1, 2 and 3 are dependent upon the amendment 2 of CTC contract, related to the availability of funds for the implementation of ACAP components, especially for the delivery of CRO and TPM. The activities point 6 is depend to the readiness of the procurement team, if the procurement of the package is ready, it will be held the CRO.

6.5 Road Safety Audit

6.5.1 No activity done during this month

6.5.2 Current status of the project for technical field as of 31 April 2014.

The Details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of April 2014 is included as Appendix B. Technical Design Review Road Safety Audit Report Status Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report AWP -2 5 Sp.Rampa – Poriaha Link No.015.xx completed completed completed completed Final Technical Report is resubmitted on 17th September 2013 6 PS.Pedati - Kerkap Link No.010.0 completed completed completed completed Final Technical Report is submitted on 17th September 2013 7 Indrapura – Tapan Link No.019.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2013 8 Bts.Pariaman – Manggopoh Link No.024.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2014 9 Rantau Tijang – Kota Agung Link No.026.1 10 Sp.Empat – Sp. Air Balam Link No.034.1 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2014 11 Bantal - Mukomuko Link No.015.2 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 12 Kambang – Indrapura Link No.017.2 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2014 13 SP.Rukis - TJ.Kemuning Link No.006.0 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga – Bts TapSel Link No.016.1 completed completed completed completed Final Technical Report is submitted on 23th September 2013 16 Seblat – Ipuh Link No.010.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th March 2014 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3