Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 51
the PMU dated 29 October 2013. Larap report has been submitted to the World Bank by PMU dated 6 November 2103, and approval from the World Bank dated 12 November 2013
that documents disclosed at PMU website.
Referring to the letter from World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding to the
approval of the report from the World Bank to be informed to Balai I North Sumatera Province. Now, PMUCTC is waiting report of implementation of the Larap from Head of
Satker PJN II North Sumatera Province.
Environmental Issues:
The UKLUPL already sent to the World Bank by PMU dated 30 September 2013.
6.6.6 Package No.06: Psr.Pedati – Kerkap
Social Issues:
CTC received a Larap report of Package no.06 Psr.Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report
during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2013 and approval the
World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revised by CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting negotiation.The final revision of Larap including signed action under submission process to
the World Bank by PMU.
Environmental Issues:
The UKLUPL has been sent to the Bank on 30 September 2013
6.6.7 Package No.07: Indrapura – Tapan
Social Issues:
CTC received from Balai IIP2JN Padang Larap report of Package no.07 Indrapura – Tapanduring on January 2014. Larap report already reviewed by CTC, and Directorate
Implementation Region I being send Memo to Balai II.
Environmental Issues:
Now CTC is waiting for and ensure the environmental safeguard for this package from Balai II PadangSubdit EA DTA.