Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 24
the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC waiting a report of Larap implementation from Head of Satker in
Lampung Province.
6. Report of LARAP for Sp. Rampa - Poriaha
Larap report for Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 and need revision as follows:
a. Moving and providing compensation for one person kiosk owner affected must including to the action plan.
b. Action plan signed by the relevan local government as a commitment that the local government will provide proper budget for the action plan
c. Implementation monitoring report by using the form provided in the LARAP. According to World Bank letter, PMU Ref. 1286Bp.11MD2013 dated 23 September 2013
has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above.
Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. Rampa – Poriaha. A revision of the Larap report already submitted to the WB from PMU
dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.
Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of
the report from the World Bank to be informed to Balai I North Sumatera. Now, PMUCTC waiting a report of Larap implementation from Head of Satker North Sumatera Province.
7. Report of Five Larap in Bengkulu
CTC recieved Larap Reports for five 5 packages in Bengkulu Province from the BBPJN III Palembang dated 30 September 2013. The five of Larapreports consists Larap for Package
No. 13: Sp. Rukis – Tanjung Kemuning, Larap for Package No. 6: Psr Pedati – Kerkap, Larap for Package No. 11: Muko-muko – Bantal, Larap for Package No. 16: Seblat – Ipuh,
Larap for Package No. 16: Bintunan – Lais.
CTC reviewed the five 5Larap Reports, and already submitted to the world bank from PMU dated 13 November 2013. All of the five Larap reports in Bengkulu Province has
reviewedbythe World Bank Ref.WINRIP144 dated 20November 2013 and need revision as follows:
a. All five Larap reports that that there are some assets land and building that will be affected entirely. Following the LARPF WINRIP should be covered on land acquisition
and resettlement and need to budgeted. b. On the Larap report for package for Ipuh – Seblat there are 126 land plots belong to
governmentpublic that are affected. However the social economic survey and the