Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 49
6.6.2 Package No.02: Padang Sawah – Simpang Empat
Social Issues:
The Larap report of Package no.02 Padang Sawah – Simpang Empat West Sumatera Province has already approved by the World Bank dated 13 January 2013, and the
monitoring report has been submitted to the World Bank by PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by
DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 5 July 2013. A monitoring report has been submitted to the World Bank by
PMU dated 15 July 2103, and approval from the World Bank dated 19 July 2013. The project Sumatera the remaining of 21 affected people did not receive compensation from
Local Government yet. Now CTC is waiting a proof of the compensation payment for 21 affected people from local government. Contract signing for the Package no.02 Padang
Sawah - Sp.Empat dated 6 Dec 2013.
Environmental Issues:
Official Letter from Director of Implementation Affairs Region I has been issued to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding to the
request of the SPPL submission. Then on 27 December 2013 SPPL document already sent to Director of Implementation Affairs Region I by Official Letter from Kepala Balai Besar
Pelaksanaan Jalan Nasional II. The SPPL document has been submitted to the World Bank on 20 January 2014.
The CTC letter to PMU
on 14
March 2014
concerning
the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on
construction stage will be done by the contractors.
6.6.3 Package No.03: Manggopoh – Padang Sawah
Social Issues:
The Larap report of Package no.03 Manggopoh - Padang Sawah West Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report
has been submitted to the World Bank by PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people did not receive compensation from Local
Government yet. CTC has received proof of the compensation payment for 5 from 15 affected people from local government. A monitoring report has submitted to the World
Bank dated 28 February 2014.
Contract signing for the Package no.03 Manggopoh – Padang Sawah dated 6 Dec 2013.
Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 50
Environmental Issues:
Official Letter from Director of Implementation Affairs Rgion I has been issued to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding to the
request of the SPPL submission. Then on 27 December 2013 SPPL document already sent to Director of Implementation Affairs Region I by Official Letter from Kepala Balai Besar
Pelaksanaan Jalan Nasional II. The SPPL document has been submitted to the World Bank
The CTC letter to PMU
on 14
March 2014
concerning
the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on
construction stage will be done by the contractors.
6.6.4 Package No.04: Ipuh – Bantal
Social Issues:
The Larap report of Package no.04 Ipuh – Bantal has already approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of
227 PAPs from Head of Satker PJN II Bengkulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank
dated 24 December 2013. Compensation payment for the remaining 70 from 227 PAP has paid by the World Bank, and a monitoring report has submitted to the World Bank dated 28
February 2014. Contract signing for the Package no.04 Ipuh – Bantal dated 14 Nov 2013.
Environmental Issues:
CTC has received copy document a SPPL report as the environmental safeguards of the package for Ipuh – Bantal from Environmental Agency BLHD and P2JN Bengkulu.
Regarding to the implementation of the Review Mission on December 9 to 11 December 2013 in Province of Bengkulu and comments from the World Bank Environmental Expert
related to the safeguards environmental documents for Package no.4 Ipuh Bantal, then based on observations in the field and the regulations required environmental safeguards
more then SPPL. Therefor the PMU has requested technical considerations from the Head of Subdirectorate of Environmental and Road Safety by the formal letter dated 16 Dec 2013.
The Sub Directorate of Environmental and Road Safety respond to PMU by Official Memo on 16 Dec 2013 that the environmental study for package No.4 was upgrade from SPPL to
UKLUPL. T
he CTC letter to PMU
on 14
March 2014
concerning
the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on
construction stage will be done by the contractors.
6.6.5 Package No.05: Sp. Rampa – Poriaha
Social Issues:
The Larap report of Package no.05 Sp.Rampa – Poriaha North Sumatera Province has already submitted to the World Bank by PMU dated 30 August 2013. The World Bank has
reviewed the report dated 16 September 2013 and required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a Larap report, and submited to