General Overview The Management Information System tasks include the following below: Database

Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 33 1. Hardcopy, the document is stored in a rack. 2. Soft files, saved in the File Storage Server. 3. Data information, inputted in database applications. For further handling that needs to be made an integrated database management system so that all data can be stored properly. The database system has been prepared to store all of WINRIP project information in a systematic, easily traceable, maintainable, and manageable format as outlined below with the following systems: a. File Storage Server, used to stored all files of reports and other documents. Please check the URL address http:storage.winrip-ibrd.com . b. Letter Database System, used to record all information of incoming and outgoing letter. c. Document Library System, used to record all information of hard copy documents then store it into library shelves. Following further review the sub‐folder server file system has been amended to accommodate the needs of the professional staff as follows: CODE ROOT 1 st FOLDER 2 nd FOLDER 01 01_Project_Document 01_01 01_01_PIP 01_02 01_02_Loan_Agreement 01_03 01_03_Loan_Agreement_Extention 01_04 01_04_PAD 01_05 01_05_PMM 01_06 10_06_Aide_Memoire 02 02_General_Contract 02_01 02_01_Pre-contract 02_02 02_02_Contract 02_03 02_03_Mobilization 02_04 02_04_Amendment 02_05 02_05_Addendum 02_06 02_06_MOA 03 03_General_Report 03_01 03_01_Inception_Report 03_02 03_02_Monthly_Progress_Report 03_03 03_03_IFR 03_04 03_04_IFR_Q 03_05 03_05_Procurement_Committee_Readin ess_ Assessment_Report 03_06 03_06_Bid_Evaluation_Procurement_Rep ort 03_07 03_07_Draft_Project_Completion_Report 03_08 03_08_Project_Completion_Report 03_09 03_09_Technical_Report Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 34 CODE ROOT 1 st FOLDER 2 nd FOLDER 04_01 04_General_Letter 05 05_General_Document ation 05_01 05_01_Meeting 05_02 05_02_Workshop 05_03 05_03_Training 05_04 05_04_Site_Visit 06 06_Office_Manager 06_01 06_01_Document 06_02 06_02_Operational 07 07_Highway 07_01 07_01_General 07_02 07_02_Design_Review 07_02_01 Package 1, 2, 3, 4 07_03 07_03_Auditor 07_03_01 Package 1, 2, 3, 4 07_04 07_04_Meeting 07_05 07_05_Report 08 08_Quality_Assurance 08_01 08_01_General 08_02 08_02_Meeting 08_03 08_03_Report 09 09_Financial 09_01 09_01_General 09_02 09_01_Meeting 09_03 09_01_Report 10 10_Environmental 10_01 10_01_General 10_02 10_02_Environmental_Review 10_03 10_03_Environmental_Studies 10_04 10_04_HIVAIDS 10_05 10_05_Monitoring 10_06 10_06_Meeting 10_07 10_07_Report 11 11_Social_Impact 11_01 11_01_General 11_02 11_02_LARAP_Review Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 35 CODE ROOT 1 st FOLDER 2 nd FOLDER 11_03 11_03_Monitoring 11_04 11_04_Meeting 11_05 11_05_Report 12 12_Procurement 12_01 12_01_General_Procurement_Notice 12_02 12_02_Special_Procurement_Notice 12_03 12_03_Bidding 12_03_01 CTC 12_03_02 DSC 12_03_03 Civil Works 12_03_04 Capacity Building 12_03_05 Disaster Management 12_04 12_04_Meeting 12_05 12_05_Report 13 13_Data_and_Informat ion 13_01 13_01_General 13_02 13_02_Source_Code 13_03 13_03_Master_Software 13_04 13_04_Meeting 13_05 13_05_Report 14 14_Community_Devel opment 14_01 14_01_General 14_02 14_02_ACAP_Review 14_03 14_03_WPM 14_04 14_04_PP3 14_05 14_05_Meeting 14_06 14_06_Report 15 15_Supporting_Staff 15_01 15_01_Tedi_Okta_Pratama 15_02 15_02_Banu_Amanda_Zuhri 15_03 15_03_Data_Manager 15_04 15_04_Bayu_Rendro Each folder will only be able to be accessed by responsible and nominated staff members to prevent any undesirable alteration or addition to the stored material. Each engineer will save every document into its correct folder which will be backed‐up weekly by the Database Specialist on a 2 TB of external hard disk. Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 36 5.3.3. Project Progress Monitoring System PPMS The application of Project Progress Monitoring System PPMS is built to stored the data of project progress every month. The project progress and financial information is retrieved from the MC Monthly Certificate that made by the contractor or consultant at submission of invoice. And we expected to know the progress status of each package will always be updated every month. In the next 3 months we are developing the PPMS application. You can see the progress with the URL address http:ppms.winrip-ibrd.com . 5.3.4. Website The official website of the WINRIP is already completed and online in August 2013. And is currently being carried update articles and documents related to the WINRIP project. Please check the URL address: http:www.winrip-ibrd.com . HOME ABOUT NEWS DOCUMENT REPORT PROCUREMENT ACAP GALLERY APPLICATION FOOTER WINRIP PMU CTC DSC Document Report Project Highway Social and Environment Community Development Procurement Progress Report Financial Report Audit Report Annual Report Progress Report Financial Report Audit Report Annual Report Procurement Plan Bidding Information Procurement Contract Goods Consultant Civil Works CHS Pengaduan CRO WPM TPM PP3 Public Information Photo Video Presenta- tion File Storage WebGIS CHS PMS Procedure Complaint Form Complaint Report Document Selection Data Report Document Selection Data Report Contact Copyright Site Map of WINRIP website. The WINRIP website contains all of the following items: a General WINRIP information including copies of all reports i.e. Monthly Progress Reports and Quarterly Progress Reports, Social and Environmental Status Reports and the Road Safety Audit Reports. b Project list and Project Progress Status including Procurement Plan and Bid Winners, and Copies of all Bid Documents. c ACAP and Complaint Handling System including contact points, list of Community Representation Observers, and list of Third Party Monitors. d Documents, including all reports and bidding documents. e Gallery and other important information. f Package Location Map. Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 37 6 PROJECT PERFORMANCE 6.1 World Bank and GOI Compliance 6.1.1 World Bank Missions No World Bank mission during March 2014

6.1.2 Performance Indicators

GOI and the World Bank have agreed on a set of Key Performance Indicators KPIs to measure the project’s performance in achieving its stated development objectives. These KPIs are provided in the World Bank’s Project Appraisal Document PAD, together with baseline data and targets. The annual targets for KPIs that are indicated in the Project Appraisal Document are based on the initial Project Implementation Schedule as shown in Appendix I. The CTC is concentrating on the establishment of precise definitions, calculation methods and data collection procedures to monitor the KPIs. 6.2 Implementation Support Components 6.2.1 Core Team Consultant CTC The CTC is responsible to provide support to the PMU and DGH in the management of the Project, based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, information management and dissemination, quality assurance and performance review for the Design and Supervision Consultants DSC, implementation and monitoring of the anti-corruption action plan, support for project monitoring and evaluation, and support for implementation of a training program to support project management and implementation. The CTC contract No. 06-20CTCTALN80431112 was signed on 5 November 2012 by both DGH and a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. Epadascon Permata Engineering Consultant. The main CTC activities during March 2014 included: • Continue assistance to PMU as and when required. • Prepare and submit Monthly Progress Report for March 2014 • Prepare for Amandment No. 2. • World Bank Meeting for Replacement Road • Finalization PQ for Package No. 11 and 13 in Bengkulu • Socialization for TPM in Bengkulu • Third Party Monitoring Review in Lampung • Monitoring LARAP Package No. 17 Sp. Gunung Kemala – Pg Tampak in Lampung Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 38 • Workshop for Updating PMM • Meeting with Pokja Bengkulu Package No. 11 and 13 • Meeting with World Bank WINRIP Coordination The following table summarized the CTC personnel field activities during March 2014. . Date Position Destination Purpose 2-3 March Community Development Officer Bengkulu Socialization Third Party Monitoring 4-5 March Senior Procurement Specialist Procurement Specialist 2 Bengkulu Finalization of PQ Result Report by Pokja for Package No. 11 : Ipuh - Bantal 5-6 March Community Development Officer Environmental Specialist Highway Engineer Ass Community Development Officer Lampung Interview Third Party Monitoring TPM 10-11 March Community Development Specialist Ass. Community Development Officer Bengkulu Interview Third Party Monitoring TPM 11-14 March Social Impact Specialist Lampung Monitoring LARAP Package No.17 Sp. Kemala-Pg. Tampak, Lampung Province

6.2.2 Design and Supervision Consultant DSC

The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II, and will be based in Padang, West Sumatera. DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March 2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.