Civil Works Implementation WINRIP DOC MPR CTC MPR No.15 2014 03 2014 03 10 00225.

Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 18 • Notice to Proceed SPMK : January 8 th , 2014 • Next PCM has been held in Banadar Lampung on February 3 rd and 5 th , 2014 2. Package Padang Sawah – Simpang Empat, West Sumatera Province, which was signed on December 6, 2013 • Contractor: Jaya Konstruksi Manggala Pertama Tbk • Notice to Proceed SPMK : January 6 th , 2014 3. Package Manggopoh – Padang Sawah, West Sumatera Province, which was signed on December 6, 2013 • Contractor: Jaya Konstruksi Manggala Pertama Tbk • Notice to Proceed SPMK : January 6 th , 2014 4. Package Ipuh – Bantal, Bengkulu Province. • Contractor: PT. Waskita Karya Persero, PT. Daya Mulia Turangga JO • Notice to Proceed SPMK on January 13 th , 2014 5. Quality Assurance Audit by Site Visit. • During March 2014, no site inspections for Quality Assurance Audit took place. • Comment on DSC and Field Team for Monthly Progress Reports: a. From July 2013 to March 2014 MPR report has not been received from the DSC. b. From January 2014 to March 2014 MPR reports no. 02 has been received from field team package no. 02 Padang Sawah – Simpang Empat only, for three other package not yet received.  Comment on field team for Monthly Progress Report no. 02 February 2014. As follow: o The Monthly Progress Report is no Progress Summary, consisting of project data, physical works progress by category, summary of works progress, progress status problem and action taken, progress monitoring curve and physical progress monitoring table.

4.4 Civil Works Progress

Civil Works can be reported on March 25, 2014, such as: a. Package 1: Biha – Krui Schedule : 1.860 Actual : 0.812 Deviation : 1.048 - b. Package 2 : Padang Sawah – Simpang Empat Schedule : 2.390 Actual : 1.024 Deviation : 1.366 - c. Package 3 : Manggopoh – Padang Sawah Schedule : 1.560 Actual : 1.020 Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 19 Deviation : 0.540 - d. Package 4 : Ipuh – Bantal Schedule : 0.560 Actual : 0.400 Deviation : 0.160 - The DSC shall is better to the Contractors of Packages that are lagging behind schedule in order that the negative slippages will not keep on piling up.

4.5 Quality Assurance

The DSC will be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. Based on the result of meeting on February 25 th , 2014 between PMU, BBPJN II, World Bank, CTC and DSC that the Manual Quality Assurance had been issued by DSC and checking by CTC. The CTC still verification the manual QA submitted by DSC with General Specification 2010.

4.6 Environmental and Social Considerations

4.6.1 Current Overall Situation

A project category is assigned to each package as either Category A, B or C depending on the likely degree of influence on environmental issues with a brief explanation as follows Appendix E. Category A project is one which will have a significant negative impact on the environment and may have an influence on areas outside the actual project area. A project classified as such requires an AMDAL ANDAL, RKLRPL study. Category B project is one which affects the people or the environment to some extent but with a smaller impact than a Category A. The required environmental analysis is a UKLUPL study only. Category C project has minimal effect on the people or environment and an environmental analysis is not required. Standard operational procedures SOP or SPPL re used to handle any minor problem which may arise.