Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 47
Date Activity
From18 March 2014 to 19 March 2014
Attendance the Meeting for PMM Project Management Manual : WINRIP Loan IBRD No. 8043-ID. at the hotel Ambarah, from 18
th
to 19
t
March 2014.
The CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer attended the meeting with the PU staffs on 18th March and 19th March 2014 in order to
discuss finalize about the Project Management Manual with the charging staffs in the PU each field in order to reflect the latest guideline, manual and methodology to implement the project.
From 17 March 2014 To 27 March 2014
Final Technical Advisory for DED which is 1 packages of AWP-2 in Bengkulu province in order to finalize technical quality review to the design preparation by DSC Attendance the
Meeting for WINRIP, at WINRIP CTC office. Final Design Technical Review of 1 package which is WINRIP AWP-3 in Bengkulu province has
carried out by the CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer in order to assess and finalize the technical quality review to the design
preparation which has prepared by DSC team, in response to recommendation of the links for betterment and their implementation under third year Annual Works Program AWP-3, and consists
of Quality Assurance Road Safety Audit of Technical Assistance for National Highway, from 17th March 2014 to 27th March 2014. and then CTC team has prepared additional Technical Design
Road Safety CAMcomment and recommendation for realistic improvement regarding DED in order to provide the last chance to the DSC team so as to change the design before actual construction of
the road.
•
Project List for Technical Advisory 1 Pacakges in Bengkulu
- No.16 SEBLAT-IPUHLink No.009.4, Bengkuliu Province
The final recommendation which is to finalize technical quality assurance in aspect of highway and road safety for DED has been submitted on 27th March 2014
6.5.2 Current status of the project for technical field as of 31 March 2014.
The Details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of March 2014 is included as Appendix B.
Technical Design Review Road Safety Audit Report Status Group
Pack No.
Name of Sub-project Technical Design Review Road Safety Audit
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
AWP -2
5 Sp.Rampa – Poriaha
Link No.015.xx completed completed completed
completed Final Technical Report is
resubmitted on 17th September 2013
6 PS.Pedati - Kerkap
Link No.010.0 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
7 Indrapura – Tapan
Link No.019.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 5th February 2013
8 Bts.Pariaman – Manggopoh
Link No.024.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 5th February 2014
9 Rantau Tijang – Kota Agung
Link No.026.1 10
Sp.Empat – Sp. Air Balam Link No.034.1
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 5th February 2014 11
Bantal - Mukomuko Link No.015.2
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013 12
Kambang – Indrapura Link No.017.2
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 5th February 2014
Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 48
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
13 SP.Rukis - TJ.Kemuning
Link No.006.0 completed completed completed
completed Final Technical Report is
resubmitted on 16th August 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed completed
Final Technical Report is submitted
on 23th September 2013
16 Seblat – Ipuh
Link No.010.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th March 2014
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues
6.6.1 Package No.01: Krui – Biha
Social Issues:
The Larap report of Package no.04 Krui – Biha Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report had been submitted to the
World Bank by PMU dated 10 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by DGH.
According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by
PMU dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Contract signing for the Package no.01 Krui – Biha dated 25 Nov 2013.
Environmental Issues:
A SPPL has already been sent to the Bank by PMU dated 30 September 2013 and t
he CTC letter to PMU
on 14
March 2014
concerning
the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on construction stage
will be done by the contractors.