All activities which have undertaken during this month

Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 47 Date Activity From18 March 2014 to 19 March 2014 Attendance the Meeting for PMM Project Management Manual : WINRIP Loan IBRD No. 8043-ID. at the hotel Ambarah, from 18 th to 19 t March 2014. The CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer attended the meeting with the PU staffs on 18th March and 19th March 2014 in order to discuss finalize about the Project Management Manual with the charging staffs in the PU each field in order to reflect the latest guideline, manual and methodology to implement the project. From 17 March 2014 To 27 March 2014 Final Technical Advisory for DED which is 1 packages of AWP-2 in Bengkulu province in order to finalize technical quality review to the design preparation by DSC Attendance the Meeting for WINRIP, at WINRIP CTC office. Final Design Technical Review of 1 package which is WINRIP AWP-3 in Bengkulu province has carried out by the CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer in order to assess and finalize the technical quality review to the design preparation which has prepared by DSC team, in response to recommendation of the links for betterment and their implementation under third year Annual Works Program AWP-3, and consists of Quality Assurance Road Safety Audit of Technical Assistance for National Highway, from 17th March 2014 to 27th March 2014. and then CTC team has prepared additional Technical Design Road Safety CAMcomment and recommendation for realistic improvement regarding DED in order to provide the last chance to the DSC team so as to change the design before actual construction of the road. • Project List for Technical Advisory 1 Pacakges in Bengkulu - No.16 SEBLAT-IPUHLink No.009.4, Bengkuliu Province The final recommendation which is to finalize technical quality assurance in aspect of highway and road safety for DED has been submitted on 27th March 2014

6.5.2 Current status of the project for technical field as of 31 March 2014.

The Details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of March 2014 is included as Appendix B. Technical Design Review Road Safety Audit Report Status Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report AWP -2 5 Sp.Rampa – Poriaha Link No.015.xx completed completed completed completed Final Technical Report is resubmitted on 17th September 2013 6 PS.Pedati - Kerkap Link No.010.0 completed completed completed completed Final Technical Report is submitted on 17th September 2013 7 Indrapura – Tapan Link No.019.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2013 8 Bts.Pariaman – Manggopoh Link No.024.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2014 9 Rantau Tijang – Kota Agung Link No.026.1 10 Sp.Empat – Sp. Air Balam Link No.034.1 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2014 11 Bantal - Mukomuko Link No.015.2 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 12 Kambang – Indrapura Link No.017.2 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 5th February 2014 Monthly Progress Report March 2014 Western I ndonesia National Roads I mprovement Project 48 Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report 13 SP.Rukis - TJ.Kemuning Link No.006.0 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga – Bts TapSel Link No.016.1 completed completed completed completed Final Technical Report is submitted on 23th September 2013 16 Seblat – Ipuh Link No.010.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th March 2014 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 completed completed completed completed Final Technical Report is submitted on 17th September 2013 20 Lubuk Alung – Sicincin Link No.009.1 21 Lubuk Alung – Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018

6.6 Environmental and Social Impact Issues

6.6.1 Package No.01: Krui – Biha

Social Issues: The Larap report of Package no.04 Krui – Biha Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report had been submitted to the World Bank by PMU dated 10 April 2013. The World Bank has reviewed the report dated 18 April 2013 required revision to be provided by DGH. According to the World Bank requested, CTC has revised a monitoring report, and submited to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank by PMU dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Contract signing for the Package no.01 Krui – Biha dated 25 Nov 2013. Environmental Issues: A SPPL has already been sent to the Bank by PMU dated 30 September 2013 and t he CTC letter to PMU on 14 March 2014 concerning the submission form monitoring RKPPL and RKLUKL for supervising the environmental management on construction stage will be done by the contractors.