Monthly Progress Report March 2014
Western I ndonesia National Roads I mprovement Project 22
schedule for these visits in attached.
4.6.2.2 Social Issues
Bengkulu Province was conducted by Environmental Specialist during 13 – 15 March 2013 to check the status of land to be acquired, to estimate of land area which is affected by the
project and to identify the type of land asset affected by project to carry out interview with PAPs, to get information related land acquisition process and to check the current status of
the Appraisal Team readiness for payment of the land acquisition. The CTC found that the land and asset of PAPs have not been paid by the project. Until the end of April 2013, the
land acquisition process is still ongoing
1. Monitoring Report of the Larap for Krui - Biha
Larap report of the package for Krui Biha in Lampung Province already approved the World Bank dated 4 January 2013, and approval the monitoring report dated 18 April 2013.
Contract signing for the package of Krui – Biha dated 25 November 2013. A pending issue is a partially affected mosque redevelopment. Initially, Local Governmentproject will rebuild an
affected mosque in parallel with construction work. In the new action, project will plan to avoid the mosque structure with shifted the central line of road because an affected structure
owner have objected if the building area to be decrease. Thus, project need to resolve land acquisition requirement on the other side of the structure position at this location.
2. Monitoring Report of the Larap for Padang Sawah – Sp. Empat
Larap report of the package for Padang Sawah – Sp. Empat in West Sumatera Province already approved the World Bank dated 13 January 2013, and approval the monitoring
report dated 19 July 2013. Contract signing for the package of Padang Sawah – Sp. Empat dated 6 December 2013. The pending issue is the remaining of 21 affected people include 5
affected people at the Air Gadang Bridge Location not yet received compensation from Local Government. Now the compensation payment for 21 affected people is being resolved
by local government. A monitoring report will be submitted to WB if ready.
3. Monitoring Report of the LARAP for Manggopoh – Padang Sawah
Larap report of the package for Manggopoh – Padang Sawah in West Sumatera Province already appovedthe World Bank dated 4 January 2013, and approval the monitoring reports
dated 18 April 2013. Contract signing for the package of Manggopoh – Padang Sawah dated 6 December 2013. The pending issue is the remaining of 10 affected people not yet
received compensation from Local Government. CTC received proof of compensation payment for 5 from the remaining of 15 affected people, and a report has been submitted to
World Bank dated 28 February 2014. Now the compensation payment for the remaining 10 affected people is being resolved by local government. A monitoring report will be submitted